Space Elevator Dynamic Response

to In-Transit Climbers

 

David D. Lang1

 

1David D. Lang Associates, Seattle WA.

 

Abstract: This presents findings of time-domain simulation studies of the space elevator using the Generalized Tethered Object Simulation System (GTOSS). Overview of mathematical models comprising GTOSS are presented. Physical configuration of the elevator as it manifests itself within GTOSS is described. GTOSS simulates climber transit by modeling chains of multiple objects and tethers, the climber being an object between two adjacent tethers, thus, climbing occurs as the earth-side tether undergoes deployment and ballast-side tether undergoes retrieval. Once an element of ribbon enters the domain of the climber, that element is no longer a participant in the free motion model of tether lying outside the climber (until it emerges). So that which is true in nature is extant within GTOSS to simulate a climber and should provide useful insight into the nature of climber design and its impact on elevator operations. The study characterizes effects on the ribbonÕs transverse, longitudinal, and libration mode oscillations due to start-up, cruise transits, and motion arrest.

 

 

1.    Introduction

 

         This paper explores the dynamic response corresponding to a variety of climber operations including: initial lift-off dynamics, nominal transits, transit resumes, and transit arrests. This study attempts to identify potential problem areas, and recommend areas for further examination. In particular, this is an exploration of dynamic attributes that could lead to ribbon failure or present operational limitations. Due to lack of concrete information on climber design, such as mass tensor properties and control system strategies, climbers are simulated as 3 (rather than 6) degree of freedom rigid bodies.

 

2.   GTOSS Overview

 

         The Generalized Tethered Object Simulation System is a time-domain dynamics simulation code, developed by the author in 1982 to provide NASA with the capability to simulate the dynamics of combinations of space objects and tethers for flight safety certification for the Shuttle Tethered Satellite System (TSS) missions. Since then, GTOSS has undergone continuous evolution and validation, being applied at some stage in the formulation of virtually every US tethered space experiment flown to date; more than 25 aerospace organizations have employed it. GTOSS was designed for generality, thus allowing its current use in simulating space elevator behavior. Below is an overview of its features.

 

¥ Multiple rigid bodies, with 3 or 6 degrees of freedom, connected in arbitrary fashion by multiple tethers, all subject to natural planetary environments, including sophisticated models for earth attributes as well as more rudimentary models for the other planets.

 

¥ Tethers represented by either massless or massive models. The massive tether model is a Òpoint synthesisÓ approach, each tether employing a constant number of up to 500 nodes, specifiable by tether (500 being a system configurable limit).

 

¥ All tethers can be deployed from, or retrieved into, objects by means of user-definable scenarios. The deployment/retrieval dynamics model includes momentum effects of mass entering or leaving the domain of the tether itself, and produces related forces on objects deploying and retrieving the tether material.

 

¥ Tethers can be defined to have length dependent non-uniform material properties. Elastic cross section, aerodynamic cross section, and lineal mass density are independently specified for up to 15 separate regions. Properties at sub-nodal points within each region are determined by interpolation. Each region can have its own modulus of elasticity and material damping attributes.

 

¥ Tethers are subject to distributed external forces arising from the following environmental effects: Aerodynamics in the subsonic and hypersonic regime; Electrodynamics due to tether current-flow interaction with the EarthÕs magnetic field using current-flow models that incorporate the earth magnetic field and effects of an insulated or bare-wire conductor interacting with the orbital plasma environment model. Note, with an appropriate ribbon-to-plasma electron contact model, this could simulate grounding-current in a conducting elevator ribbon.

 

¥ Tethers experience longitudinal thermal response. Tethers gain heat under the influence of solar radiation, earth albedo, earth infrared radiation, aerodynamics, and electrical currents; heat loss occurs through radiative dissipation.

 

¥ Tethers can be severed at multiple locations during simulation.

 

¥ Objects and tethers can be initialized in many ways, including creating stabilized extremely long tether chains, attached to and rotating with a planet (a space elevator) with due consideration for non-uniform tether properties and the concomitant longitudinally varying strain distribution of elastic tether material.

 

¥  GTOSS creates a database containing results of response to the user-defined material configuration, initialization specifications, and environmental options; this permanent data base can then be post processed to produce a wide variety of result displays, from tabular data, to graph plots, to animations.

 

 

3.     Climber Simulation Rationale

 

         Construction and operational payload climbers traversing the ribbon will excite transverse and longitudinal string mode responses and elevator libration motion (the simple pendulum-like motion of the elevator about its anchor point). Such responses will reflect all the potentially non-linear effects related to tapered ribbon design, inverse-square gravity field, centrifugal forces, Coriolis effects, atmospheric disturbance, and climber speed modulation.

         GTOSS possesses the ability to simulate a climberÕs transit of the ribbon by modeling chains of multiple objects and tethers. The climber would be an object in a chain with two adjacent tethers, the earth-side tether undergoing appropriate deployment, while the ballast-side tether undergoes complimentary retrieval (for upward climbing). An argument in behalf of this approach starts with the fact that once an element of ribbon enters the "domain of the climber" (ie. gets clenched-in and/or threaded-through rollers, etc.), and until it emerges, that element is within the domain of the climber itself, thus, not a participant in the free dynamic motion of the ribbon lying outside the climber. Such a state of affairs appears to meet all the pertinent criteria for application of a tether deployment/retrieval simulation. So that which is true in nature is extant within GTOSS to simulate climber action. In further affirmation of this viewpoint, note that ribbon strain distribution internal to the climber will, in general, be unlike that of adjacent external ribbon because unique strain states can be imposed upon the ribbon within the climber mechanism; indeed, exceeding limit-strain within the climber may be a factor in climber traction designs that engage the ribbon through overlapping roller schemes to take advantage of capstan effects. Intuitive reasoning opposed to the above climber simulation rationaleÕ and based on a priori knowledge of ribbon continuity must be tempered by the fact that as far as external ribbon dynamics are concerned, there could just as well be a recycling plant within the climber ingesting ribbon from above, re-synthesizing it to make a new ribbon, and deploying it out the bottom.

         For climber studies, the GTOSS configuration consists of a climber containing two reels of ribbon, both of which characterize the ribbonÕs dual taper design. Earth-side deployment occurs such that the earth-end taper would emerge first, while for the upward deployed ribbon, the ballast-end would emerge first. In this way, no matter where the climber is positioned, the ribbon below and above properly portray the total earth-to-ballast profile.

         Conventionally, deployment conjures up images of a reel positioned at altitude, with ribbon being dropped down; that is not what is occurring during climber operations. To clarify, consider two points, P1 and P2, between which ribbon is to be dispensed. Two  distinct processes can accomplish this, process A and B. In process A, the reel is positioned at P2 remaining stationed there with the ribbon  spooled-off and dragged to P1. In process B, the reel starts at P1, and is then transported to point P2, with ribbon being laid-down between P1 and P2. These are dynamically distinct processes, in that if observed from a location fixed between P1 and P2, the following would be noted: in process A, there would be a continuous parade of different ribbon particles traversing by, while for process B,  a single particle of ribbon would appear at the observation point, and remain there throughout the deployment. Process B is realized by GTOSS climber simulation both above and below the climber.

 

4.   GTOSS Space Elevator Physical Properties

 

         By using appropriate definitions of tether properties above and below the interior climber-object, GTOSS is made to reflect the design profile properties along the entire elevator. Conveniently, since each finite tether model can have independent properties, assigning a different number of nodes to each tether can provide dissimilar nodal resolutions at different regions of ribbon if desired.

         Ribbon characteristics vary with length, and are comprised of: density, elastic-area, modulus, aerodynamic-area, and damping, all corresponding to baseline ribbon design as described in References 1 and 2. The ballast mass is 634,000 kg at a radius of 100,000 km. The climber mass corresponds to the nominal 20 ton design; attributes for inertia tensor, control effectors, etc., are currently un-defined, so the climber is simulated with 3 (rather than 6) degrees of freedom. The elevatorÕs tapered ribbon is initialized by GTOSS to a stabilized vertical state with ribbon strain distribution in equilibrium with gravity, centrifugal, and attached climber loads. The dual tapered ribbon is designed to achieve, over its entire length, a uniform stress distribution of about half of the 120 giga Pascal capability anticipated for operations. GTOSS confirms this as shown by the unloaded ribbonÕs stress profile in figure 1 below.

Figure 1.  Ribbon Stress vs Altitude

 

         This uniform stress results from GTOSS simulation of the interplay between planetary environments and the ribbonÕs tapered  cross sectional profile, modulus, and density (shown in the figures below). The slight droop in the stress curve near the earth can be attributed to approximation errors associated with curve-fitting the ribbon profileÕs taper gradient near the earth.

Figure 2.  Ribbon Elastic Cross Sectional Area vs Altitude

         Based on elastic cross sectional area profile and a nominal value of ribbon materialÕs bulk density of 1.3 gm/cm3 (CNT), the lineal density profile shown in figure 3 below was derived for use in GTOSS.

Figure 3. Ribbon Density vs Altitude

 

5.   Case Definitions and Simulation Results:

 

Unless otherwise specified, the following definitions apply:

 

 (a).  Nominal climber Transit speed is 200 km/hr.

 

 (b). Nominal Lift-off or Transit-resume is defined as a one hour duration linear ramp-up from zero to nominal transit speed.

 

 (c). Nominal Arrest is defined as a one hour duration linear ramp-down from nominal transit speed to zero.

 

 (d). Sudden Arrest is a step change from transit speed to zero speed.

 

All Transit and Arrest cases start with a stable transit in progress. All Liftoff or Transit-resume cases start with zero rate.

             

         Case 1: Nominal Payload Liftoff from Ground (1 hr  ramp-up).

 

         Case 2: Limit Payload Liftoff from Ground  (1 hr ramp-up).

 

         Case 3: Transit Resume from GEO (1 hr ramp-up).

 

         Case 4: Nominal Transit to Ballast (200 km/hr).

 

         Case 5: Fast Transit to Ballast (400 km/hr).

 

         Case 6: Nominal Transit to GEO (200 km/hr).

 

         Case 7: Sudden Arrest at 2 km (zero ramp-down time).

 

         Case 8: Modulated Arrest at 2 km (60 sec ramp-down time).

 

Case 1:      Nominal Liftoff from Ground (1 hour ramp up).

 

         This case shows the mechanism by which nominal climber liftoff can occur. A 20 ton climber weighing 178,035 N on the launch pad will experience a ribbon tension from above of 197,000 N and from below of 19,700 N. Before liftoff, the climber net weight (gravity less centrifugal force) is in equilibrium with this tension differential across the climber. While this tension differential allows practical liftoff acceleration to occur, it also represents the maximum possible liftoff acceleration. The mechanism by which the tension in the lower ribbon is exploited for liftoff consists of the climberÕs transporting ribbon from above itself to below. An element of ribbon length, when transported from the domain of the upper ribbon has very little effect upon the strain in the upper ribbon due to that ribbonÕs extreme length, thus tension is correspondingly affected but little due to the low effective spring rate of the upper ribbon. On the other hand, that same parcel of ribbon, when introduced into the domain of the lower ribbon, has a profound effect upon its strain state due to the lower ribbonÕs short length, thus, a correspondingly greater effect upon the lower tension due to the lower ribbonÕs high spring rate. Transport of ribbon from above to below, can cause an immediate and significant drop in lower ribbon tension; this in turn creates an imbalance on the climber accelerating it upwards. Once the lower ribbon becomes slack, then the maximum possible immediately available force imbalance on the climber will have been realized. Any additional acceleration can only come from increasing strain in the upper ribbon. Figure 4 below depicts a nominal liftoff.

 

Figure 4. Climber Liftoff vs Time

As seen in figure 4 above, tension at the ground dips down initially as the climber starts transporting upper ribbon into the lower ribbon domain. This tension drop, that can be easily and quickly induced, provides the initial upward force imbalance that starts the climber in motion. In spite of upper ribbon continuing to flow into the lower domain, the lower tension starts to increase due to upward climber motion continually separating the lower ribbon attach points, thus tending to neutralize strain reduction that caused the tension to drop initially, as shown in figure 5 below.

 

Figure 5. Average  Strain in Lower Ribbon vs Time

 

         During the liftoff acceleration period, the upper ribbon is very slowly acquiring a tension increase due to the strain increase brought about by the climberÕs continual removal of ribbon from the upper domain; also at work is the general gravity/centrifugal effect that brings about the characteristic concave-down tension-versus-altitude profile of the elevator. The oscillations seen in the these figures is associated with the fact that the liftoff scenario employed was not designed to control longitudinal oscillations. Since the end-to-end ribbon transmission time for a stress disturbance is about an hour, with the first longitudinal mode having a period of about 2 hours, it is evident that stress disturbances, once initiated, will periodically manifest themselves at the site of the initial disturbance and longitudinal oscillations will exhibit (2 hr) periodicity.

         Upper and lower ribbon climber tensions are compared in figure 6 below. It is seen that upper tension also drops initially, with both tensions following a similar profile in time. The initial drop in upper tension is because the climber starts accelerating upward under the force imbalance due the immediate reduction of lower tension. Even though the climber is transporting equal increments of ribbon length from the upper into the lower domain, such increments arenÕt nearly as effective in increasing tension above as it is in lowering tension below. Both tensions, continue to rise and converge, finally peaking and coalescing to a zero differential at GEO.

 

Lower Ribbon at Climber

 

Upper Ribbon at Climber

 

 

Figure 6. Upper and Lower Tension at the Climber vs Time

 

 

         Figure 7 below shows tension observed at 50 km altitude on the ribbon. The discontinuous change at 0.75 hours is where the climber passes 50 km point.

Tension after Climber passage

 

Tension prior to Climber passage

 

Figure 7. Tension at 50 km Altitude vs Time

 

         The climber itself progresses up the ribbon with only slight westward horizontal displacement as shown as libration angle relative to local vertical in figure 8 below. This libration is due to Coriolis effects, and its steady diminishing is likely attributable to geometry of increasing altitude combined with steady tension increase (above and below) that provides some restoring stiffness against horizontal displacement.

 

Figure 8. Climber Libration vs Time

 

 

Case 2:      Limit Payload Liftoff from Ground.

 

         This explores repercussions of attempting climber launch at the maximum weight the elevator can support, a situation in which  the lower ribbon has essentially zero initial tension. Unlike Case 1, the only means to effect liftoff in this situation is to ÒclimbÓ the upper ribbon, a process equivalent to increasing upper ribbon tension alone to effect liftoff and subsequent transit velocity.

         Figure 9 below shows a set of related liftoff parameters (note, a somewhat different set of parameters are presented than shown in figure 4.)

 

 

Tension just above climber

 

Tension just below climber

 

No tension

 

40 km of loose ribbon on Launch Pad

 

Actual Climber altitude

 

Lower ribbon length

 

Climber altitude catches up

with lower ribbon length

 

Figure 9. Liftoff Parameters vs Time

 

Since the lower ribbon tension is initially near zero, the process of transferring ribbon into the lower domain to effect a tension differential is no longer effective; only increasing strain in the upper ribbon will act to effect liftoff. This is clearly not an operationally feasible scheme, since it operates the elevator at a transiently unstable load condition capable of pulling down the ballast.

         The lower ribbon is observed to go slack for about 1.5 hours; by the time ribbon transfer-rate has ramped to its nominal value, the climber has deposited 40 km of slack ribbon on the ground. Albeit an inefficient means of creating tension differential, removing this amount of ribbon from the upper domain has increased upper tension to eventually accelerate the climber to an altitude equal to the amount of slack ribbon below; this increase is not obvious at the tension scale in figure 9. At the point climber altitude matches the (heretofore slack) ribbon length below, a severe impact event occurs creating a longitudinal strain disturbance seen to manifest itself on the order of every 2 hours at the climber, consistent with the round-trip stress wave propagation time to the ballast. At first impact, altitude rate is twice nominal transit rate. The climber quickly acquires nominal rate after impact transients subside, as shown in figure 10 below.

Stress-wave round trip

propagation time

 

Figure 10. Climber Altitude Rate vs Time

 

 

Figure 11 below shows snapshots of the impact disturbance at various times as it progresses along the ribbon.

Figure 11. Tension Snapshots vs Altitude along Ribbon

 

 

Note, the climber progresses up the ribbon less than 1% of the total ribbon length during the 4 hours of simulated time.

         This case clearly exhibits the fact that creation of immediate and significant climber acceleration cannot exceed a level corresponding to a force equal to the initial tension at the climber interface with the lower ribbon; in fact, smooth and timely liftoff operation depends upon this initial lower tension. Thus, once a design acceleration is specified, then maximum liftoff mass of the climber is determined. This will likely not constitute a significant operational constraint since the time to accelerate to nominal transit speed is likely not a critical design parameter provided a reasonable level is possible, and it seems that it is.

 

 

Case 3:      Transit Resume from GEO (1 hour ramp-up).

 

         This case examines a climber resuming to nominal transit speed from a parked position at GEO. Starting from 35,400 km altitude, the climber ribbon rate ramps up to nominal over a period of one hour. Figure 12 below shows the resulting altitude and climb rate response, and indicates that a resume to transit

 

 

Figure 12. Climber Altitude and Rate vs Time

 

speed is feasible from GEO. This situation presents a different situation than liftoff from ground. The mechanism that creates altitude rate, while intrinsically the same at ground or GEO, is not as immediate or as effective at GEO. It is apparent, from the periodic oscillations in the altitude rate, that the climber is interacting with the ribbonÕs first longitudinal natural mode. In equilibrium at GEO, before a transit resume, the climber would have the same tension above as below. Ribbon is still transferred from above to below to create a tension differential, but it is unlike ground liftoff where upper ribbon being transferred to the lower ribbon causes an immediate and significant tension drop below but little tension increase above. At GEO, this ribbon transport process has nearly equal effectiveness above and below for creating tension change. Figure 13 below shows upper and lower tensions at the climber. Meaning can be extracted from this apparent meandering behavior if the differential in these two tensions are examined.

Tension

 Above

 

Tension

 Below

 
 

 

Figure 13. Tension Above and Below Climber vs Time

 

         This tension differential, shown in figure 14 below, represents the forcing function that creates vertical climber acceleration. During the initial 1 hour ramp-up of ribbon transfer-rate, the net vertical tension differential is increasing to

 

Ramp-up

ends

 

 

Figure 14. Tension Differential Across Climber vs Time

 

accelerate the climber. At one hour, ribbon transfer rate has arisen to the constant nominal transit speed and at that point an oscillation manifests itself in the differential tension, with a period characteristic of the first longitudinal mode of the ribbon. The ribbon transfer scenario used in this study has made no attempt to minimize coupling with the first longitudinal mode, as may be possible with proper climber design. Unlike transverse string modes, longitudinal modes inherently induce strain rate, thus might be effectively controlled with internal material damping.

 

 

Case 4:      Nominal Transit to Ballast at 200 km/hr.

 

         Figure 15 below presents an overview of a 200 km/hr transit of essentially the entire length of the elevator from 2,000 to 98,000 km.

 

Transit Arrest

 

Dotted line is Ballast

Solid line is Climber

 

 

Figure 15.  2,000 to 98,000 km Climber Transit @ 200 km/hr  vs Time

 

The characteristic oscillations in the altitude rate starting at about 450 hours represents the longitudinal response of the climber-ribbon combination to a linear ramp-down transit arrest. This is an artifact of the arbitrary arrest scenario used in this study, and likely would be suppressed with a well designed climber-arrest control strategy. The elevatorÕs 5 day in-plane (east-west) libration period manifests itself throughout transit indicating a progressively westward retrograde bias under the influence of Coriolis effects on the climber until climber transit arrest; then, starting from the arrest state-conditions, a new phase of libration develops, symmetrical about the vertical. So the net overall effect on the elevator as a whole, due to this particular full length climber transit and arrest, is to have induced a net libration of about +/- 0.55 degrees.

         The resulting libration appears to be dependent upon when the arrest actually occurs. From examination of figure 15, up until arrest occurs at 450 hours, the developing libration oscillation has points of zero libration rate; if arrest completes at a zero libration-rate-point, the resulting libration of the elevator simply acquires the corresponding amplitude as its initial condition (and maximum amplitude). Thus based on time-of-arrest for this transit, it appears that a net libration between +/- 0.3  and +/- 0.65 degrees could have resulted.

         Figure 16 below shows climber altitude rate oscillations at arrest, using a magnified time scale to expose an approximately 6 hour period of oscillation. The climber, since it arrests very near the ballast mass, excites the ballastÕs longitudinal bobbing mode; due to the dominating ballast mass, this mode can be visualized as a one degree-of-freedom spring-mass system comprising the ballast mass and an effective end-to-end ribbon spring rate of 0.04 N/m. The smaller periodic irregularities are likely related to longitudinal-mode interaction with the

1 hour arrest starts

 

Figure 16. Climber Altitude Rate after Arrest vs Time

 

climber mass now parked very near the ballast.

         Compared to gross elevator libration, the climber is producing insignificant transverse string-mode displacements as seen in figure 17 below depicting snapshots taken throughout the 28 days of simulated time. Here, each snapshot simply appears as a straight line.

 

 

Figure 17. Ribbon Snapshot Envelope vs Distance along Ribbon

 

Figure 18 below depicts a shape snapshot with greatly magnified horizontal scale

Indicates gross

    Libration

 

Climber location

 

Figure 18. Ribbon Displacement Snapshot vs Distance along Ribbon

 

showing transverse displacement at 2 days into the transit (10,000 km). Though appearing as a solid line, this snapshot consists of dots, each being a nodal point. At the time of this snapshot, nodal density is far greater between the climber and ground than between climber and ballast; by the end of the transit, just the opposite will be true. Figure 19 below shows that normal climbing produces virtually no over-stress. At 450 hrs, arrest maneuver stress oscillations are seen.

 

Figure 19. Ribbon Stress Profile vs Distance along Ribbon

 

 

Case 5:      Fast Transit to Ballast at 400 km/hr.

 

         Figure 20 below presents an overview of a 400 km/hr transit of essentially the entire length of the elevator from 2,000 to 98,000 km.

 

Dotted line is Ballast

Solid line is Climber

 

Figure 20.  2,000 to 98,000 km Climber Transit @ 400 km/hr  vs Time

      

         It is notable that this particular 400 km/hr transit induced libration angle about twice that of the 200 km/hr transit. However, unlike the previous 200 km/hr case, it appears that this arrest occurs at a more advantageous libration state; had arrest occurred at the most inopportune time, then up to +/- 1.3 degrees of libration may have resulted. The general effect of increasing transit rate appears to be an increase in westward bias, or slope of the average libration angle while under transit rate; peak-to-peak libration excursions during transit are more or less invariant at about 0.3 degree. This mean that regardless of optimal arrest timing, faster transits will always result in more residual elevator libration.

         An interesting effect is seen in the transit-arrest disturbance induced at 98,000 km as it propagates to lower altitudes on the ribbon. Figure 21 is a stress time history at 5,000 km and 50,000 km altitude, indicating a disturbance magnification factor of three. Under close examination, this disturbance is found to consist of; stress waves being propagated up and down the ribbon, bobbing mode response of the ballast, and excited longitudinal modes. This magnification might be attributable to two effects, (a) an increase in tension level as the strain

             

Stress at  50,000 km

 

Climber passes 50,000 km

 

Climber passes 5,000 km

 
 

 

Figure 21.  Ribbon Stress at 2 Altitudes vs Time

 

energy encounters ribbon of smaller elastic cross section (similar to the increase in ocean wave height as wave energy encounters narrowing land-constraints), (b) for a given disturbance tension level, an increase in stress due to smaller elastic cross section of the ribbon.

 

 

Case 6:      Nominal Transit to GEO at 200 km/hr.

 

         Figure 22 below presents libration response of a 200 km/hr transit from 2,000 km to GEO altitude (35,400 km); note, general response was typical of the

 

Region of interest

 

Dotted line is Ballast

Solid line is Climber

 

Arrest

 

Figure 22. Elevator Libration vs Time

 

other transits. It may be possible to modulate transit rate to arrive at GEO arrest with near zero libration (note ÒRegion of interestÓ above), a fact that could have benefit for elevator operations. Note that the act of climbing induces transverse vibrations of the ribbon as shown in figure 23 below that depicts a snapshot of

 

Ribbon transverse string

mode displacement at Climber near GEO is less than 10 km

 

Ballast Libration

  displacement

 

Figure 23. Ribbon snapshot: Total Displacement from Vertical vs Altitude

 

ribbon displacement just before GEO arrest. From figure 23, it can be concluded that by the time the climber nears arrival at GEO, about 10 km of transverse string displacement has been induced; this corresponds to about 0.002 deg deflection (as viewed from ground). Given that gross elevator libration at this point is on the order of 0.1 degrees, this transverse deflection does not appear to be operationally significant at this transit speed. Transverse string response can translate into equivalent librations since, like libration, it is a manifestation of momentum disturbance in the horizontal direction. Note also that the restorative effects of ribbon tension toward keeping the climber aligned between anchor and ballast are operationally insignificant due to the very small angles that the ribbon makes with the line-of-sight between ballast and anchor (note axis scaling in figure 23).

 

 

Case 7:      Sudden Arrest at 2 km.

 

         This case examines response of a climber at full transit speed of 200 km/hr experiencing a sudden arrest. Starting at 1 km, the climber maintains full speed for 18 sec until, at which point, ribbon transport rate becomes instantly zero at 2 km altitude. Figure 24 below shows the response.

 

Sudden arrest altitude

 

Region of rebound under influence of upper ribbon

 

Climber slowly rebounds under

upper ribbon tension

 

Climber is catapulted downward by high

impact tension with the lower ribbon

 

Figure 24. Climber Altitude and Altitude Rate vs Time

             

         The response is characterized by the climber first engaging against the stiff spring of the lower ribbon and being catapulted back downward in reverse to immediately put the lower ribbon in a state of slack; this is followed by a slower rebound upward under the influence of the softer spring of the upper ribbon; these two processes then cyclically repeat while attenuating due to damping. The difference in upper and lower spring rates is clearly seen in the altitude rate graph above. Figure 25 below shows tension history at two ribbon points.

Tension @ 20,000 km

 

Tension @ 1.5 km

 

  Disturbance finally appears @20,000 km

 

arrest

 

 

Figure 25. Ribbon Tension at 1.5 km and 21,000 km vs Time

 

Tension at 1.5 km exhibits load spikes characteristic of impact loading. Note that at 20,000 km, the ribbon does not experience this transient until almost 10 minutes after the sudden arrest has occurred below it on the ribbon.

 

              Figure 26 shows a magnified display of details of the initial impact.

 

Initial impact peak load

 

2nd rebound against lower ribbon

 

Lower Ribbon is Slack

as climber rebounds via

upper ribbon tension

 

Sudden arrest

 

Climber passes 1.5 km

 

 

Figure 26. Ribbon Tension at 1.5 km Altitude  vs Time

 

         While this response is certainly not desirable, figure 27 below shows why it could be disastrous. It is apparent from this stress time history, that the design strength of the ribbon, including the factor-of-safety of 2, is seriously threatened by the sudden arrest load.

 

Approaching Ultimate Load

 

Figure 27. Ribbon Stress at 1.5 km Altitude  vs Time

                           

This is good reason for climber mechanism design and liftoff speed modulation scenarios to eliminate possibility of such an event.

 

 

Case 8:      Modulated Arrest at 2 km.

 

         This case is identical to Case 7, except, a gentler 60 sec ramp down to zero rate is employed. Figure 28 shows the response to such an arrest.

 

Figure 28. Climber Altitude and Altitude Rate vs Time

 

The resulting stress time history at 1.5 km, is shown in figure 29 below; compare this with figure 27 above.

 

Arrest completes

 

Arrest starts

 

Climber passes 1.5 km

 

Figure 29. Stress @ 1.5 km vs Time

 

         There are many possible arrest scenarios to optimize aspects of climber operations; the above arrest is arbitrary, primarily illustrating that practical scenarios can be easily designed to bring about transit arrest in a reasonable time, even at low altitude, without threatening the ribbon strength.

 

 

6.    Conclusions

 

         The major operational effect of a climber transit is seen to be due to the Coriolis dynamics as the climber ascends. The residual libration resulting from a transit appears to be a function of both the speed and distance of the transit, as well as when the transit arrest occurs relative to the libration cycle being induced throughout the transit. As a rule, faster transit causes greater libration.

         This study points out the potential effects of simultaneous climber interactions with both a very low effective end-to-end spring-rate of an elevator ribbon of full length, and the high spring rates associated with shorter ribbon sections extant near the ground at liftoff. This manifests itself in a variety of elevator climbing operations, but most dramatically in the process of both accelerating and decelerating a climber on the ribbon, specially in near-ground operations such as liftoff. The longitudinal string modes of vibration were found to be easily excited under climber acceleration or deceleration. Bobbing mode frequencies of the ballast mass, as well as climber mass can manifest themselves in response to climber activity. Stress wave propagation effects are also seen to manifest themselves.

 

 

7.     Future Work

 

         Many areas of new investigation regarding climber transit were identified, but left unaddressed by this preliminary study. Noting that passive (i.e., non-horizontal-thrusting) transits leave a residual libration artifact in the elevator, there may be significant issues concerning how these artifacts will accumulate or be controlled over successive transits during long term operations. Will it be possible to plan transit launch phasing to minimize residual levels of libration without undesirable impact on transit schedules? Can transit speed modulation and arrest timing be used effectively to minimize resulting libration? If elevator traffic models were to include a (roundtrip) shuttling schedule between earth and LEO, then how might these trips be phased to take advantage of the reverse-Coriolis effect on the way down in order to control residual libration of the elevator? What is an acceptable level of libration? What are optimal lift-off scenarios? Rigid body response of climbers interacting with: atmospheric loads, ribbon string modes, and elevator libration may have impact on beamed-power system design, and should be addressed.

 

 

Acknowledgements

 

         Funding for this work has been provided by the Institute for Scientific Research, Fairmont, WA.

 

References

 

1.  Edwards, Bradley C., Westling, Eric A.  ÒThe Space ElevatorÓ, published by Spageo Inc, San Francisco, CA, 2002.

 

2. Edwards, Bradley C., unpublished communications with the author.

 

3. Pearson, Jerome, ÒThe Orbital Tower: a Spacecraft Launcher Using the EarthÕs Rotational EnergyÓ, Acta Astronautica. Vol. 2. pp. 785-799