The Evolution of the

DOE ORR EM Public Participation
A. A. Brooks - 1945, 1956-1997

Public Participation in Oak Ridge has developed in stages:

1 - Don't Ask, We Don't Tell - 1942 to 1982

2 - Talk To - 1982 to 1992

3 - Talk With - 1992 -1994

4 - Talk With, Listen To - 1994 to 1996

5 - Talk With, Listen To, Explain Non-Responses - 1997

6 - Talk With, Listen To, Accept Advice, Explain - 1998

7 - The DOE, EPA, and TDEC Final Decisions - ????

8 - Public Participation is Automatic without Prompting


Abstract and Conclusions

Public participation in the affairs of the Department of Energy (DOE) Environmental Management (EM) program on the Oak Ridge Reservation (ORR) has evolved slowly and at times painfully. It has progressed from non-existent to an almost fully developed stage. Its remaining shortfalls involve both the Environmental Protection Agency (EPA) and the Tennessee Department of Environment and Conservation (TDEC). These shortfalls are openly acknowledged by DOE and are being openly discussed. Improvements will be forthcoming. Clearly, excellent, productive public participation occurs at ORR. It has taken a long time but DOE acknowledges its worth.


Stage 1 - Don't Ask, We Don't Tell

This stage, from 1942 to 1982, which added up to Ignore, was derived from the classified nature of the early ORR missions. It was also a period when the nature of radioactive pollutants was not well understood. There is little evidence that there was any general, callous neglect of worker or public health. When the two major off-site releases, i.e., radioactivity to the Clinch River and mercury to the East Fork Poplar Creek, were discovered, immediate steps were taken to reduce them. In fact, there is adequate evidence that considerable attention was given to the prevention of environmental contamination even during wartime. The transition from the classified environment to an open environment was to be difficult.


Stage 2- Talk To - 1982 to 1992

This stage started with a forced release (Freedom of Information Act) of information on the contamination of Lower East Fork Creek by large amounts of mercury. Once past the original hurdle, DOE did a reasonable job of keeping the public informed. When LEFPC became a Superfund site in 1986, DOE adopted the CERCLA required procedures for public involvement. By 1992, it became apparent that the Oak Ridge public had a lot to say as well as the capacity to listen and understand the issues. It was also apparent that some of the public were dissatisfied with the risk assessment of the LEFPC, and said so, often bluntly.


Stage 3 - Talk With - 1992 -1994

In 1992 to their credit, DOE formed a LEFPC Citizens' Working Group under David Page, the project manager. Though the CWG had a fixed membership, it had open public participation and Mr. Page and his staff went out of their way to aid in the presentation of all points of view including the opposition. In a July 1994 meeting with EPA, the stakeholders presented their technical arguments. Dr. Elmer Akin explained the EPA regulatory risk assessment model and its use of biased data as well as the public's right of protest during the subsequent risk management phase. This defined the nature of future public efforts, it turned to a political effort based on technical reasons.


Stage 4 - Talk With, Listen To - '94 to '96

This stage includes an event in 1992, the WAG 6 public meeting, at which the public strongly opposed the $140 million asphalt cap on the grounds it did not decrease the risks. Brief but important, it set the pattern for the LEFPC CWG. The LEFPC cemented the trend in that the public mustered the necessary, vocal attendance at the January 1995 LEFPC public meeting to convince the regulators that the proposed 180 ppm mercury level was conservative and it should be changed upwards. It was changed to 400 ppm with savings upwards of $150 million. ORR public participation would never regress to its former state. DOE knew beyond a doubt that the public's input on balance was sound and constructive. Above all, it was appreciated.


Stage 5 - Talk With, Listen To, Explain Non-Responses

This stage is characteristic of the DOE CERCLA procedures wherein there is a requirement after the major decisions are made to obtain public comment, both oral and written. The responses are given (and lost) in a formal report with little opportunity for the public to explain how they were misunderstood. This mode of public interaction simply is not suitable for complex remediation projects where much of the concern is for the technical basis of the remediation and for the cost-effectiveness of a truly complex total project. Fortunately, this stage was brief because DOE recognized, as the public had claimed, that early and extended participation was necessary if mutual understanding was to be reached, and trust established.


Stage 6 -Talk With, Listen To, Accept Advice, Explain

This stage started in 1996, after a brief lull, with discussions of the then "Ten Year Plan" assumptions. It started early and comprised a series of excellent meetings with constant feedback. A great deal of credit is due Mark Musolf and Marianne Heiskel for eliciting diverse opinion and its excellent reception. Curiously, much but not all of the discussion, was about the clarification of wording and simplification of the document. The experience was actually enjoyable. These discussions continued in the same vein on the topic of the 1998 budget document. Early in 1997, the End Use Working Group was formed through SSAB under Doug Sarno, its capable facilitator, Karen Bowdle and with DOE's Margaret Wilson and many dedicated assistants.


Stage 6 Continued - The End Use Working Group

This arduous public effort deserves special mention because it deals with so many complex aspects of the entire ORR Environmental Management Program. Although its final recommendations are related to contaminated land use, it must consider the geology and environment of the waste sites, the technical feasibility and cost of proposed remediations, long-term stewardship and questions of inter-site equity in order to make sound recommendations. This is being done with DOE's assistance but without their domination. The community goals developed and the recommendations presented do not necessarily agree with DOE, EPA and TDEC preferences. The ORNL Surface Impoundment ponds are an example. This leads to Stage 7.


Stage 7 - The DOE, EPA and TDEC Final Decisions?

The final selection of the remediation alternative is arcane. The public hears differing reports and knows neither whether its recommendations were well presented and argued nor why the contrary actions were selected. It does not even know who was primarily responsible, DOE, EPA, or TDEC. After spending thousands of hours in preparing its positions, the public deserves better reporting and a place at the table. After all, the Public does accept the risks and pays the bills. Currently (Dec 1997), this problem is openly acknowledged by DOE, which promises progress.

Late Flash: A recent open dialogue with EPA and TDEC promises much improved public participation.

More on this and other ORR Environmental Management projects can be found on: http://home.comcast.net/~brooks50/

About the Author: The author is a retired chemist who owns about five acres of pasture on the mercury-contaminated LEFPC floodplain. He has participated in these ORR processes as a wartime and post-wartime, prime contractor employee, as an owner of contaminated land, as a public participation advocate and as an antagonist to the EPA biased risk assessment and other distortions of science. In spite of outspoken comments against the establishment's positions, he enjoys a friendly working relationship with DOE management and much of the regulatory community. He is a member of the SSAB End Use Working Group, the Citizens' Advisory Panel of the Local Oversight Committee, Inc. and of the Environment Committees of the League of Women Voters of Oak Ridge and the Friends of ORNL. His retirement now consists of meetings, meetings, meetings ...


 Structure of the ORR Stakeholders Organizations

Orginal poster display converted to this hierarchical form.

The Oak Ridge Reservation Stakeholders
Local Oversight Committee, Inc. - FFA
    Board - comprising County & City elected Executives
   Citizens Advisory Panel - comprising Board appointed Citizens
        
Sub-Committees

DOE ORO EM Site Specific Advisory Board - FACA
         comprising DOE Appointed Citizens
      
Sub-Committees & Working Groups

There are additional active Stakeholder Groups at ORR. FFA is the Federal Facilities Agreement between DOE, EPA and Tennessee. FACA is the Federal Advisory Committee Agreement.