

The
foundation walls were constructed of concrete block which followed the
pattern of the walls on the first floor, making a very complicated arrangement.
In order to avoid the bottom of the swimming pool sitting in ground water,
we added one more course of blocks to the entire house. The plumbing
was roughed in, and the entire foundation was then filled with sand and
gravel, topped off with sheets of plastic and finally reinforcing bars.

The swimming pool arrived on a truck, and was lowered into its place.
It had to be in place before the slab was poured.
Fortunately,
we had good weather for the pouring of the slab. All in all, it was
a pretty big piece of concrete. In the foreground of the picture
is the garage, which is required to be a few inches lower than the rest of
the house.
Shortly after the slab had set up completely,
the dome kit arrived on a large flatbed truck. We hired a neighbor who had a
forklift to unload the pieces and move them back to the building site.



The
dome framing went up pretty quickly with the help of son-in-law Mike.
The procedures were outlined clearly in the instructions which came with the kit. The importance
of scaffolding cannot be overestimated; it would have been virtually
impossible to accomplish much of the work without it.

After
the sheathing was placed on the dome, it was possible to remove the stabilizing
struts which up until now had been positioned over the openings to the future
extensions. (The large pits are for the planters for the palm trees and other
tropical plants which were eventually placed in the foyer.)
We then began to add the
extensions, of which there were five: the foyer and front porch, the living room (which
is shown rising at the right of the picture), the dining room, the guest
bedroom (showing a bit at the left), and the pool room. The most
complicated of these was the pool room, which because of its length required
additional steel supports.

When
the extensions were complete, the garage was framed out, and the sheathing
(half-inch plywood) was put in place. Then the entire roof area and
all walls were covered with tarpaper.



When
all the facing was in place, we started to paint it the Cape Cod Grey that
we had decided would fit best with the grey bark of the trees.
Since this was winter, painting was restricted to very warm days.
We
hired a neighbor to level out the driveway , using the sandy dirt which
had been dug out during the installation of our septic system..
We then had him spread grey stone over the dirt, so finally we had a real
driveway (and less dirt in the house).
Return
to the Domestic Photo Album