Element
Minor changes made in equipment
FGB work is 5 months behind schedule
Grapple added to FGB for SPP assembly
Computers shipped for FGB
Power converters delivered for FGB
Backup FGB control center to be added to NASA JSC
Subsystem assmebly continues
FGB declared complete
FGB completed on schedule & on budget
FGB damaged in pressure testing
Node-1/Unity
Fixes for structural flaws costs $40 M
Working 3 shifts 7 days a week to recover lost schedule
Passive thermal components in production
Hand rails and restraints delivered
PMA-1
PMA-2
Service Module/Zvezda
Russia given 6 weeks to provide financing for module
Data System with RKA agreement final
Z1 Truss
P6 Truss
PV Arrays & Radiators
Flight mast canisters delivered & in test
Alpha Rotary Joints under construction
E-Wing qualification unit in testing
Alpha Rotary Joint STA testing underway, desing review held
US Lab
Machining complete
First wire harness completed
Lab model passes paint tests - Air purification tests successful - power control software delivered
Hatches fabricated
Lab cost overruns
Comm system cost overruns
Lab painted
Lab moved to NASA MSFC
Pressure testing completed
First flight cables produced
SSMRS
MPLM
US Airlock
Major components welding underway
Component welding mostly complete
Equipment Lock Components complete
Equipment Lock hull welding complete
Docking Compartment 1
S0 Truss
S1 Truss
Science Power Platform
P1 Truss
P3 Truss
P4 Truss
Docking Compartment 2
JEM
Universal Docking Module
S3 Truss
S4 Truss
Docking & Stowage Module
Research Module 1
Research Module 2
S6 Truss
US Habitation Module
Life Support Module 1
Life Support Module 2
Centrifuge Accomidation Module
CRV / CTV
Dridging phase provides additional technical data
ARD assembly and testing underway
Phase B procurment approved, X-CRV discussed
ARD nearly complete
Program changes from ESA capsule to NASA lifting body
4 person craft considered
ARD
APM (Columbus Orbital Facility)
European Robotic Arm
Research Module 3
Progress M1
Progress M2
Soyuz TM
LTV
LTV needed for station control but delays expected
LTV plans dropped
ATV
Discussions and studies with the Russian Space Agency on interfaces & subsystems
ATV/ISS interface draft complete
ATV final review
ICM
Astronaut Activities
International Cooperation & Program Management
US-Russian discussions of funding crisis
SPP launch traded for Soyuz Modifications
NASA to increase funding to Russia
2 additional STS-Mir flights to aid Russian space funding
ISS electrical system review held
ISS Incremental Design Review was held in Houston
Goldin ultimatum to Russia
Annual IDR completed
New assembly sequence completed
Cost overruns mount
Revised IGA's and MOU's nearing completion