|
Element |

|
Jan/Feb
|
March/April
|
May/June
|
July/Aug
|
Sept/Oct
|
Nov/Dec
|

|
|
FGB / Zarya |
|
FGB
delivered to Energia
End
to end tests developed, MDM failures investigated
|
|
FGB
& Proton shipped to Baykonur
Testing
completed, MDM's being changed
|
|
Final
astronaut training in FGB
FGB
readied for launch
|
RSA
requests FGB orbit change to co-orbit with Mir
NASA
denies orbit change
FGB
launched
Minor
problems on orbit
|
 |
|
Node-1 / Unity & PMA-1 & PMA-2 |
 |
|
Final
testing underway
Software
is on critical path
|
|
|
Shuttle prepared for launch |
Node
launch date finalized
First
launch attempt aborted
Node-1
launched
docked
to FGB
assembly
EVA's completed
shuttle
lands
|
 |
|
Service Module / Zvezda |

|
SM
on schedule
SM
may be delayed, April tests critical
Goldin
confident schedule will not be impacted by delays
RSA
arranges for SM subcontractors to deliver without immediate payments
|
SM
design problems addressed
SM
2 months late but has aggressive schedule to recover, funding
planned for 1998
SM
is 4 months late
Computers
delayed
Some
1997 funding still withheld, 1998 funding not reaching contractors
SM
and US Lab are equally delayed
|
Telemetry
system is critical path, side port modfied for refuelling
DMS-R
qualification review completed
Khrunichev
delivers SM to Energia, takes out loans to pay fof work done
Funding
shortages continue
Training
and integration for SM inadaquate
Full
1997 funding received
Meteroid
shield fixes criticised
|
RSA needs $50-100M by Sept. for SM |
Funding
shortage to cause new delays
SM
2 to 2.5 months late
NASA
to buy $60M in Russian services to provide for SM completion
DMS-R
software testing completed
SM
lacking critical components
$60M
from NASA dependant on contingency plan
|
Quality
of work in doubt
60%
of electrical tests completed
July
launch may slip to September
DMS-R
software delays CDR
|
 |
|
ICM |
 |
|
Requirements
and function defined
ICM
decision to replace SM to be made in May
ICM
modifications rule out docking to FGB
|
ICM
decision to replace SM to be made in July
Decision
on docking to FGB or SM to be made later this year
Several
resupply options considered along with ICM
|
SM replacement decision deffered on July
15 |
|
|
 |
|
Progress M1 |
 |
|
Projected flight rate exceeds avionics production |
The first 3 flight units are on schedule |
Production
has virtually stopped
NASA
plans for shuttle modifications for ISS reboost
|
|
|
 |
|
Z1 Truss |
 |
Z1 launch preparations begin |
|
|
Problems cause testing delays |
|
|
 |
|
PMA-3 |
 |
PMA-3 arrives at KSC |
|
|
|
|
|
 |
|
P6 Truss |
 |
|
P6 being prepared for launch |
|
|
|
|
 |
|
PV Arrays |
 |
|
|
|
|
|
|
 |
|
Soyuz TM |
 |
|
Modifications
made to dock to FGB
Projected
flight rate exceeds avionics supply
|
Additional Soyuz modifications, first 3
flight units on schedule |
Soyuz
supply will not be meet demand
Soyuz
production all but stopped
|
NASA negotiates to buy 2 Soyuz |
|
 |
|
US Lab |
 |
|
Lab
delayed 1.5 months
Lab
is 3 months late
Lab
will be 4-6 months late
Parts
unavailability delays Lab several months
Major
communications problems fixed
|
Lab
is 6 weeks late
Thermal
control problem increases delays
|
Schedule 'recovery' over the summer has
stopped due to problems |
|
|
 |
|
SSRMS |
 |
|
|
|
|
|
|
 |
|
MPLM |
 |
|
Testing and qualification reviews underway,
ECLSS units delivered |
|
Leonardo arrives at KSC |
ECLSS changes delay final reviews and require
changeout of Leonardo equipment at KSC |
Leonardo MPLM formally transfered to NASA |
 |
|
US Airlock |
 |
|
Airlock
2 months late
External
storage added to airlock
|
|
|
|
|
 |
|
Docking Compartment 1 |
 |
|
|
|
|
|
|
 |
|
S0 Truss |
 |
|
|
Parts shortages threaten construction |
|
|
|
 |
|
S1 Truss |
 |
|
|
|
|
|
|
 |
|
Science Power Platform |
 |
|
Discussions to test SPP at KSC underway |
|
|
|
|
 |
|
P1 Truss |
 |
|
|
|
|
|
|
 |
|
Universal Docking Module |
 |
|
|
|
|
Ukrainian or Chinese module could be attached
to UDM |
UDM
to be all new FGB type design incorporating Life Support Module
features
Work
to begin on hull before design is complete
|
 |
|
P3 Truss |
 |
|
|
|
|
|
|
 |
|
P4 Truss |
 |
|
|
|
|
|
|
 |
|
Docking Compartment 2 |
 |
|
|
|
|
|
|
 |
|
S3 Truss |
 |
|
|
|
|
|
|
 |
|
S4 Truss |
 |
|
|
|
|
|
|
 |
|
Node 2 |
 |
|
Node-2 structures to be more durable than
US modules, and provides more storage space |
Second design review defines requirements
for modules |
Node-2 design changes as a habiat module
substitute will delay delivery |
|
Configuration changes delaying delays |
 |
|
Propulsion Module |
 |
|
24 month development schedule possible |
Decision tree and funding planning underway |
Boeing
requested to propose service module replacement
Proplusion
module , ATV and HTV may replace SM propulsion
|
|
|
 |
|
JEM |
 |
|
|
|
|
|
|
 |
|
Docking & Stowage Module - 1 |
 |
|
|
2 small modules consolidated into single
module |
|
|
|
 |
|
Docking & Stowage Module - 2 |
 |
|
|
2 small modules consolidated into single
module |
|
|
|
 |
|
Docking & Stowage Module |
 |
|
|
Khrunichev
takes over Energia roll
FGB
design to be used
DSM
to incorporate life support systems
FGB-2
to become DSM
|
|
|
|
 |
|
Node 3 |
 |
|
Duplicate habitat systems in Node-3 and
US Hab module increase program costs $125M |
Second design review defines requirements
for modules |
Design Review finalizes Node-3 as temporary
habitat module |
|
Manufacturing of structural model begun |
 |
|
APM (Columbus Orbital Facility) |
 |
|
COF system PDR complete |
Structure
manufacture begun
Operations
and support facility plans seriously delayed
|
|
Component qualification tests & SW delays |
COF mass exceeds plans, action plan to resolve |
 |
|
Research Module 1 |
 |
|
Russia decides on 2 Soyuz class research
modules instead of 3 |
|
|
Design still moving away from Zenit to Soyuz
class module |
Ukraine may help Russia develop a Zenit
class research module |
 |
|
Research Module 2 |
 |
|
Russia decides on 2 Soyuz class research
modules instead of 3 |
|
|
|
|
 |
|
Life Support Module 1 |
 |
|
|
Module replaced by UDM |
|
|
|
 |
|
Life Support Module 2 |
 |
|
|
Module replaced by UDM |
|
|
|
 |
| CRV / CTV |
 |
NASA
reafirms ESA role in X-38 project
Aerothermodynamics
database work done by ESA, ESA states sign up for CRV work, aft
structures and nose for V201 under construction
|
7
person CRV added to budget, X-38 studied as potential CRV
First
X-38 drop test successful
X-38
is 10 months behind schedule, transition of work to CRV developement
not well defined
|
Complete recosting for CRV to be done in
2000, X-38 and CRV management to be integrated |
13 ESA V-201 components indetailed design |
|
NASA-ESA cooperation plan signed |
 |
|
S6 Truss |
 |
|
|
|
|
|
|
 |
|
European Robotic Arm |
 |
1-2
month delay due to computer, ends and joints, Base points shipped
to Energia, Water tank model readied for shipment to TsPK in
April
Full
scale model shipped
|
Flight unit 2 months behind schedule, Training
software prototype completed |
|
6 month delay in delivery to RSA to July
2000 |
|
Joint delays and SPP delays projected |
 |
|
HTV |
 |
|
|
|
Japan plans HTV to provide dry goods resupply |
|
|
 |
|
Centrifuge Accomidation Module |
 |
|
Japan to provide CAM for JEM launch |
|
|
|
|
 |
|
Transhab |
 |
|
|
Alternative Hab module in development |
|
|
|
 |
|
US Habitation Module |
 |
|
|
|
|
|
|
 |
| Cupola 1 & 2 |
 |
|
|
|
Cupola's to be constructed by ESA to pay
for Express pallet launches |
Cuploa
deal finalized for 5 Express transports and COF improvements
Industry
proposals due
|
Development kick-off |
 |
|
ATV |
 |
|
ATV
included into ISS traffic model
Preliminary
Authorisation to Proceed, RSA barter for ATV and DMS-R drafted
|
Moscow
meeting reveals significant problems in barter deal
Cargo
accomodation concept completed
|
6
ATV's planned
ATV
could also dock to Node-3, Russia differs on barter, Phase C/D
contract completed
|
|
|
 |
|
ARD |
 |
|
|
ARD
ahipped to Kourou in June
ARD
on schedule for July launch
Communications
test successful
|
|
Launch on Oct 21, flight successful |
|
 |
|
Multipurpose Module |
 |
|
|
|
|
MOU signed for sale of FGB-2 to USA |
|
 |
|
Astronaut Activities |
 |
ESA astronaut corp planning meetings take
place |
ESA astronaut corp formed merging national
programs |
ESA corp grows, new shuttle training agreement |
ESA corp grows, COF training defined |
|
|
 |
|
International
Cooperation & Program Management |
 |
MOU
signed by 16 nations participating in ISS
General
Designers Review held in Moscow, assembly schedule change due
in April
|
RSA
1998 budget fails to inclide ISS funding
Barter
deals among international partners to offset costs of launch
and resupply
Software
development key to 1998 ISS schedule
ISS
2 years lat and $3B over 1993 plans
Engineering
changes slipping out of control, KU comm pointing system costs
double
MEIT
creeps back into program increasing costs and delays
|
Yeltsin
orders Ministers to fund ISS
Software
development and testing, subcontractor parts delivery delays
monitored closely
SSCB
and Agency heads agree to new Rev. D assembly schedule
More
slips projected even before Rev. D schedule is announced
Boeing
5 weeks late overall, software fixes for HW problems common,
Russians agree to common international approach to crew training
Integrated
International SW integration schedule proposed
Air
leak rates cause concern for resupply, Russia proposes high standard
favoring their HW designs
Russia
looks for commercial funding for ISS, replaces 4 Soyuz class
modules with 1 FGB class module
Almost
no 1998 funding received by RSA, Soyuz and Progress production
all but stopped
|
Soyuz
and Progress flights in Rev. D can't be provided by Russia, more
delays inevitable
NASA
looks for future Russian services and product to buy to inject
funds for current developments
|
NASA asks for $60M for purchase of future
Russian deliverables to pay for current project needs |
Ukraine
announces agreement to build Russian Research module 1 or 2 based
on Zenit class module
SSCB
and Heads of Agency review assembly sequence, update due next
spring
|
 |