Element

 Jan/Feb

 March/April

 May/June

 July/Aug

 Sept/Oct

 Nov/Dec

FGB / Zarya

FGB delivered to Energia

End to end tests developed, MDM failures investigated

 

FGB & Proton shipped to Baykonur

Testing completed, MDM's being changed

 

Final astronaut training in FGB

FGB readied for launch

RSA requests FGB orbit change to co-orbit with Mir

NASA denies orbit change

FGB launched

Minor problems on orbit

 Node-1 / Unity & PMA-1 & PMA-2 

Final testing underway

Software is on critical path

Shuttle prepared for launch

Node launch date finalized

First launch attempt aborted

Node-1 launched

docked to FGB

assembly EVA's completed

shuttle lands

Service Module / Zvezda

SM on schedule

SM may be delayed, April tests critical

Goldin confident schedule will not be impacted by delays

RSA arranges for SM subcontractors to deliver without immediate payments

SM design problems addressed

SM 2 months late but has aggressive schedule to recover, funding planned for 1998

SM is 4 months late

Computers delayed

Some 1997 funding still withheld, 1998 funding not reaching contractors

SM and US Lab are equally delayed

Telemetry system is critical path, side port modfied for refuelling

DMS-R qualification review completed

Khrunichev delivers SM to Energia, takes out loans to pay fof work done

Funding shortages continue

Training and integration for SM inadaquate

Full 1997 funding received

Meteroid shield fixes criticised

RSA needs $50-100M by Sept. for SM

Funding shortage to cause new delays

SM 2 to 2.5 months late

NASA to buy $60M in Russian services to provide for SM completion

DMS-R software testing completed

SM lacking critical components

$60M from NASA dependant on contingency plan

Quality of work in doubt

60% of electrical tests completed

July launch may slip to September

DMS-R software delays CDR

ICM

 

Requirements and function defined

ICM decision to replace SM to be made in May

ICM modifications rule out docking to FGB

ICM decision to replace SM to be made in July

Decision on docking to FGB or SM to be made later this year

Several resupply options considered along with ICM

SM replacement decision deffered on July 15    

 Progress M1

  Projected flight rate exceeds avionics production The first 3 flight units are on schedule

Production has virtually stopped

NASA plans for shuttle modifications for ISS reboost

   

  Z1 Truss

Z1 launch preparations begin     Problems cause testing delays    

 PMA-3

PMA-3 arrives at KSC          

 P6 Truss

  P6 being prepared for launch        

 PV Arrays

           

 Soyuz TM

 

Modifications made to dock to FGB

Projected flight rate exceeds avionics supply

Additional Soyuz modifications, first 3 flight units on schedule

Soyuz supply will not be meet demand

Soyuz production all but stopped

NASA negotiates to buy 2 Soyuz  

 US Lab

 

Lab delayed 1.5 months

Lab is 3 months late

Lab will be 4-6 months late

Parts unavailability delays Lab several months

Major communications problems fixed

Lab is 6 weeks late

Thermal control problem increases delays

Schedule 'recovery' over the summer has stopped due to problems    

 SSRMS

           

 MPLM

  Testing and qualification reviews underway, ECLSS units delivered   Leonardo arrives at KSC ECLSS changes delay final reviews and require changeout of Leonardo equipment at KSC Leonardo MPLM formally transfered to NASA

 US Airlock

 

Airlock 2 months late

External storage added to airlock

       

 Docking Compartment 1

           

 S0 Truss

    Parts shortages threaten construction      

 S1 Truss

           

 Science Power Platform

  Discussions to test SPP at KSC underway        

 P1 Truss

           

 Universal Docking Module 

        Ukrainian or Chinese module could be attached to UDM

UDM to be all new FGB type design incorporating Life Support Module features

Work to begin on hull before design is complete

 P3 Truss

           

P4 Truss

           

 Docking Compartment 2

           

 S3 Truss

           

 S4 Truss

           

Node 2

  Node-2 structures to be more durable than US modules, and provides more storage space Second design review defines requirements for modules Node-2 design changes as a habiat module substitute will delay delivery   Configuration changes delaying delays

Propulsion Module

  24 month development schedule possible Decision tree and funding planning underway

Boeing requested to propose service module replacement

Proplusion module , ATV and HTV may replace SM propulsion

   

 JEM

           

Docking & Stowage Module - 1

2 small modules consolidated into single module

 Docking & Stowage Module - 2

    2 small modules consolidated into single module      

Docking & Stowage Module

Khrunichev takes over Energia roll

FGB design to be used

DSM to incorporate life support systems

FGB-2 to become DSM

 Node 3

  Duplicate habitat systems in Node-3 and US Hab module increase program costs $125M Second design review defines requirements for modules Design Review finalizes Node-3 as temporary habitat module Manufacturing of structural model begun

 APM (Columbus Orbital Facility)

COF system PDR complete

Structure manufacture begun

Operations and support facility plans seriously delayed

  Component qualification tests & SW delays COF mass exceeds plans, action plan to resolve

Research Module 1

  Russia decides on 2 Soyuz class research modules instead of 3     Design still moving away from Zenit to Soyuz class module Ukraine may help Russia develop a Zenit class research module

Research Module 2

  Russia decides on 2 Soyuz class research modules instead of 3      

 Life Support Module 1

    Module replaced by UDM      

 Life Support Module 2

    Module replaced by UDM      
 CRV / CTV

NASA reafirms ESA role in X-38 project

Aerothermodynamics database work done by ESA, ESA states sign up for CRV work, aft structures and nose for V201 under construction

7 person CRV added to budget, X-38 studied as potential CRV

First X-38 drop test successful

X-38 is 10 months behind schedule, transition of work to CRV developement not well defined

Complete recosting for CRV to be done in 2000, X-38 and CRV management to be integrated 13 ESA V-201 components indetailed design   NASA-ESA cooperation plan signed

 S6 Truss

     

European Robotic Arm

1-2 month delay due to computer, ends and joints, Base points shipped to Energia, Water tank model readied for shipment to TsPK in April

Full scale model shipped

Flight unit 2 months behind schedule, Training software prototype completed 6 month delay in delivery to RSA to July 2000 Joint delays and SPP delays projected

HTV

Japan plans HTV to provide dry goods resupply

Centrifuge Accomidation Module

  Japan to provide CAM for JEM launch        

Transhab

Alternative Hab module in development

US Habitation Module

Cupola 1 & 2 Cupola's to be constructed by ESA to pay for Express pallet launches

Cuploa deal finalized for 5 Express transports and COF improvements

Industry proposals due

Development kick-off

ATV

ATV included into ISS traffic model

Preliminary Authorisation to Proceed, RSA barter for ATV and DMS-R drafted

Moscow meeting reveals significant problems in barter deal

Cargo accomodation concept completed

6 ATV's planned

ATV could also dock to Node-3, Russia differs on barter, Phase C/D contract completed

ARD

ARD ahipped to Kourou in June

ARD on schedule for July launch

Communications test successful

Launch on Oct 21, flight successful

Multipurpose Module

    MOU signed for sale of FGB-2 to USA  

  Astronaut Activities

ESA astronaut corp planning meetings take place ESA astronaut corp formed merging national programs ESA corp grows, new shuttle training agreement ESA corp grows, COF training defined    

 International Cooperation & Program Management

MOU signed by 16 nations participating in ISS

General Designers Review held in Moscow, assembly schedule change due in April

RSA 1998 budget fails to inclide ISS funding

Barter deals among international partners to offset costs of launch and resupply

Software development key to 1998 ISS schedule

ISS 2 years lat and $3B over 1993 plans

Engineering changes slipping out of control, KU comm pointing system costs double

MEIT creeps back into program increasing costs and delays

Yeltsin orders Ministers to fund ISS

Software development and testing, subcontractor parts delivery delays monitored closely

SSCB and Agency heads agree to new Rev. D assembly schedule

More slips projected even before Rev. D schedule is announced

Boeing 5 weeks late overall, software fixes for HW problems common, Russians agree to common international approach to crew training

Integrated International SW integration schedule proposed

Air leak rates cause concern for resupply, Russia proposes high standard favoring their HW designs

Russia looks for commercial funding for ISS, replaces 4 Soyuz class modules with 1 FGB class module

Almost no 1998 funding received by RSA, Soyuz and Progress production all but stopped

Soyuz and Progress flights in Rev. D can't be provided by Russia, more delays inevitable

NASA looks for future Russian services and product to buy to inject funds for current developments

NASA asks for $60M for purchase of future Russian deliverables to pay for current project needs

Ukraine announces agreement to build Russian Research module 1 or 2 based on Zenit class module

SSCB and Heads of Agency review assembly sequence, update due next spring