Element
FGB / Zarya
Node-1 / Unity & PMA-1 & PMA-2
Service Module / Zvezda
7/24 Integration tests slipping schedule
delay likely to Sept.
SM prepared for shipping to Baykonur, delay likely to Sept.
Launch possible before year end
Recent delays due to errors not lack of funding
SM shipped to Baykonur, passes initial tests
SM launch delay likely to Sept./ Oct.
DMS-R for NASA SW testing
HW flaw in DMS-R, requires new HW & SW
SM power spikes require DMS-R changes
SM on schedule
Delays due to shuttle
further delays due to shuttle problems
Major software flaw fixed
Proton failure leaves SM launch in doubt
SM has high noise levels
DMS-R boot problem fixed
ICM
Progress M1
Z1 Truss
PMA-3
P6 Truss
PV Arrays
Soyuz TM
US Lab
SSRMS
MPLM
US Airlock
Docking Compartment 1
S0 Truss
S1 Truss
P1 Truss
Science Power Platform
P3 Truss
P4 Truss
S3 Truss
S4 Truss
Universal Docking Module
Docking Compartment 2
Node 2
Propulsion Module
JEM
Docking & Stowage Module
HTV
Node 3
APM (Columbus Orbital Facility)
European Robotic Arm
SW & HW development delays flight unit to Q4 2000
CDR completed, changes to be made by October
CRV / CTV
V201 flight article under construction
Development 6 months late
ARD
S6 Truss
Centrifuge Accomidation Module
Cuploa 1 & 2
Research Module 1
Research Module 2
Enterprise
LTV
US Habitation Module
ATV
Multipurpose Module
Astronaut Activities
Expedition 0 crew may be considered for manual SM-FGB docking
European astronaut assigments and ISS training begun
Expedition 0 crews named
Expedition 0 crew training effecting Expedition 1
Expedition 3 crew named
Expedition 5 crew named
Expedition 0 crew may be used to 'finish' Service module on orbit
Astronauts train on Service module
International Cooperation & Program Management
Program contingency plans drafted
Top administrators leave program
NASA plans for $100M procurments from Russia
Russia saya no misappropriation of NASA funding for Soyuz 204
Soyuz 204 being sent to Mir
ISS assembly sequence E complete