Another week has gone by and there does not appear to be much progress - at least visibly.
There is sheeting on the entire house - except for the North wall. The HVAC folks got started and installed the trunks upstairs and got their holes cut for the vents.
The fascia is done, shingles are completed, soffits are about 45% done and they started on the porch.
We met with an electrician and he got us the needed shopping list.
I removed some of the electrical from the utility room. I still need to remove the gas line and the water lines from the floor in order to fix up the floor.
Dad came over and helped me move stuff into storage. We have nearly emptied 2 rooms now. Hopefully when we have to cut down the ceilings there will not be too much stuff to move around.
Margaret and I went to Home Depot and bought all of the electrical and a new water heater. Later we went to Menards and ordered all the interior and exterior doors with 2 exceptions. We spent thousands of dollars on Saturday.
We expect HVAC and electrical work to resume on Monday.
There is sheeting on the entire house - except for the North wall. The HVAC folks got started and installed the trunks upstairs and got their holes cut for the vents.
The fascia is done, shingles are completed, soffits are about 45% done and they started on the porch.
We met with an electrician and he got us the needed shopping list.
I removed some of the electrical from the utility room. I still need to remove the gas line and the water lines from the floor in order to fix up the floor.
Dad came over and helped me move stuff into storage. We have nearly emptied 2 rooms now. Hopefully when we have to cut down the ceilings there will not be too much stuff to move around.
Margaret and I went to Home Depot and bought all of the electrical and a new water heater. Later we went to Menards and ordered all the interior and exterior doors with 2 exceptions. We spent thousands of dollars on Saturday.
We expect HVAC and electrical work to resume on Monday.