| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Define Problem | 5 days | Fri 2/11/05 | Thu 2/17/05 | | 0% |
| 2 | Research Feasability | 5 days | Fri 2/11/05 | Thu 2/17/05 | | 0% |
| 3 | Business Case | 1 day | Fri 2/11/05 | Fri 2/11/05 | Analyst | 0% |
| 4 | Analyze Request for Proposal | 1 day | Mon 2/14/05 | Mon 2/14/05 | Analyst | 0% |
| 5 | Develop Solution Statement | 3 days | Fri 2/11/05 | Tue 2/15/05 | Designer | 0% |
| 6 | Develop Statement of Assumptions | 1 day | Fri 2/11/05 | Fri 2/11/05 | Developer | 0% |
| 7 | Develop Statement of Limitations | 1 day | Mon 2/14/05 | Mon 2/14/05 | Developer | 0% |
| 8 | Develop High-Level Organization of Project | 1 day | Tue 2/15/05 | Tue 2/15/05 | Analyst | 0% |
| 9 | Project a Delivery Date of Project | 1 day | Tue 2/15/05 | Tue 2/15/05 | Developer | 0% |
| 10 | Develop a Statement of Major Acquisitions | 1 day | Wed 2/16/05 | Wed 2/16/05 | Developer | 0% |
| 11 | Develop a Summary of Cost | 1 day | Wed 2/16/05 | Wed 2/16/05 | Analyst | 0% |
| 12 | Develop a Return on Investment (ROI) Statement | 1 day | Thu 2/17/05 | Thu 2/17/05 | Analyst | 0% |
| 13 | Develop a Cash Flow Analysis Statement | 3 days | Tue 2/15/05 | Thu 2/17/05 | Administrative Assistant | 0% |
| 14 | Deliver Feasabilty Report | 0 days | Thu 2/17/05 | Thu 2/17/05 | | 0% |
| 15 | Analyze Situation | 15 days | Fri 2/18/05 | Thu 3/10/05 | | 0% |
| 16 | Hire Staff | 6 days | Fri 2/18/05 | Fri 2/25/05 | Developer | 0% |
| 17 | Form User Workgroups from different departments | 2 days | Mon 2/28/05 | Tue 3/1/05 | Analyst | 0% |
| 18 | User workgroups interview users in each department | 3 days | Wed 3/2/05 | Fri 3/4/05 | Designer | 0% |
| 19 | Meeting to form Rough Requirements Document | 1 day | Mon 3/7/05 | Mon 3/7/05 | Designer | 0% |
| 20 | Rough Requirements Document is reviewed in each department | 2 days | Tue 3/8/05 | Wed 3/9/05 | Analyst | 0% |
| 21 | Meeting to finalize Requirements Document | 1 day | Thu 3/10/05 | Thu 3/10/05 | Designer | 0% |
| 22 | Deliver Requirements Document | 0 days | Thu 3/10/05 | Thu 3/10/05 | | 0% |
| 23 | Design Solution | 10 days | Fri 3/11/05 | Thu 3/24/05 | | 0% |
| 24 | Acqurie Resources | 2 days | Fri 3/11/05 | Mon 3/14/05 | Developer | 0% |
| 25 | User Group Meeting to review progress | 6 days | Wed 3/16/05 | Wed 3/23/05 | | 0% |
| 26 | User Group Meeting to review progress 1 | 1 day | Wed 3/16/05 | Wed 3/16/05 | Designer | 0% |
| 27 | User Group Meeting to review progress 2 | 1 day | Wed 3/23/05 | Wed 3/23/05 | Designer | 0% |
| 28 | Develop Prototype | 2 days | Tue 3/15/05 | Wed 3/16/05 | Developer | 0% |
| 29 | Develop User Manuals | 4 days | Fri 3/11/05 | Wed 3/16/05 | Trainer | 0% |
| 30 | Test Prototype | 2 days | Thu 3/17/05 | Fri 3/18/05 | Developer | 0% |
| 31 | Meeting to form Rough Specification Document | 1 day | Mon 3/21/05 | Mon 3/21/05 | Designer | 0% |
| 32 | Rough Specification Document is reviewed in each department | 2 days | Tue 3/22/05 | Wed 3/23/05 | Analyst | 0% |
| 33 | Meeting to finalize Specification Document | 1 day | Thu 3/24/05 | Thu 3/24/05 | Designer | 0% |
| 34 | Deliver Specification Document | 0 days | Thu 3/24/05 | Thu 3/24/05 | | 0% |
| 35 | Implement Design | 20 days | Fri 3/25/05 | Thu 4/21/05 | | 0% |
| 36 | User Group Meeting to review progress | 16 days | Wed 3/30/05 | Wed 4/20/05 | | 0% |
| 37 | User Group Meeting to review progress 1 | 1 day | Wed 3/30/05 | Wed 3/30/05 | Designer | 0% |
| 38 | User Group Meeting to review progress 2 | 1 day | Wed 4/6/05 | Wed 4/6/05 | Designer | 0% |
| 39 | User Group Meeting to review progress 3 | 1 day | Wed 4/13/05 | Wed 4/13/05 | Designer | 0% |
| 40 | User Group Meeting to review progress 4 | 1 day | Wed 4/20/05 | Wed 4/20/05 | Designer | 0% |
| 41 | Develop User Manuals | 20 days | Fri 3/25/05 | Thu 4/21/05 | Trainer | 0% |
| 42 | Test Product | 20 days | Fri 3/25/05 | Thu 4/21/05 | | 0% |
| 43 | Lab environment | 6 days | Fri 3/25/05 | Fri 4/1/05 | Developer | 0% |
| 44 | Limited Roll-out in non-critical areas | 6 days | Mon 4/4/05 | Mon 4/11/05 | Developer | 0% |
| 45 | Meeting to review testing results | 1 day | Tue 4/12/05 | Tue 4/12/05 | Designer | 0% |
| 46 | Roll-out in critical areas in parallel with existing service | 6 days | Wed 4/13/05 | Wed 4/20/05 | Developer | 0% |
| 47 | Meeting to review tested product | 1 day | Thu 4/21/05 | Thu 4/21/05 | Designer | 0% |
| 48 | Implement Tested Product | 0 days | Thu 4/21/05 | Thu 4/21/05 | | 0% |
| 49 | Support Product | 10 days | Fri 4/22/05 | Thu 5/5/05 | | 0% |
| 50 | Train users in each department | 4 days | Fri 4/22/05 | Wed 4/27/05 | Trainer | 0% |
| 51 | Hire permanent staff to maintain product | 8 days | Fri 4/22/05 | Tue 5/3/05 | Analyst | 0% |
| 52 | Prepare documentation for product | 9 days | Fri 4/22/05 | Wed 5/4/05 | Designer | 0% |
| 53 | Print User Manuals for existing emplyees and new-hires | 8 days | Fri 4/22/05 | Tue 5/3/05 | Administrative Assistant | 0% |
| 54 | Develop Mainenance Plan | 9 days | Fri 4/22/05 | Wed 5/4/05 | Developer | 0% |
| 55 | Meeting to examine process (What went right? What went wrong?) | 1 day | Thu 5/5/05 | Thu 5/5/05 | Analyst | 0% |
| 56 | Deliver Maintenance Plan | 0 days | Thu 5/5/05 | Thu 5/5/05 | | 0% |