
October
2, 2001
We arrived at The
Plantation about 10 AM today. The trip from Massachusetts was uneventful.
Jean, our Sales Person, helped us settle in to a rental house. She found
this for us while we were in Massachusetts and did a wonderful job of
matching our needs. This will be our home during The Holidays of 2001
while our Waterbridge Court Home is constructed.

October 3, 2001
This is the first day of
our Home Building Adventure. The sun rose over what will be the pool side
of the house. The house has been laid out and the forms for the slab have
been started. This is “The Beginning” for us.
We spent the day unpacking
and getting settled in to our rental home. It Pine Hill Neighborhood. We
are renting from Marilyn and Bill who also live in The Plantation. It is a
very nice home and will serve us perfectly.
We spent some time with
Marilyn and Bill and also our new Waterbridge Court neighbors – Eileen
and Gary. They were all very helpful in pointing out the various areas and
people we need to know. We learned from people at
“The Construction Office” that our permits are still with “The
County” and they are waiting their return.

October
9, 2001
We are getting comfortable
with our surroundings and Linda is participating in several activities.
She is meeting people quickly. Our permits are still not
back and we have been advised not to bother “them.” So – the
activity at Waterbridge #1 has been limited. The last two days, they have
put in all the plumbing that will be in the slab. Lots of pipes – all
PVC. Our van is parked in front of "the garage."

October
11, 2001
There has been no further
activity on the house. The Permits are still not back. Duncan and I did
wander around the lot and even out along the Palatlakaha River for a
while. We didn’t see any alligators, but we knew they were there – we’ve
seen them in the past. There is a dam just upstream from us. The dam
provides The Plantation with water control for most of the property. This
is a view from the dam back to the Plantation Boulevard bridge.
October 12, 2001
They have been busy at the
house today. They’ve treated all the ground with an insect killer of
some sort and then
covered it all with a
thick, poly vapor barrier. They’ve been installing rebar in all the
footings. They also put a Portable John on the lot. I’m told this is a
sure indication that they are committed and increased activity is
imminent.

October 15, 2001
There has been little
activity for the last couple of days. We're told that they won't pour
until the permit is back. They’ve finished the forms and it is ready for
concrete. Everything looks good. This view is from the corner of the lot
nearest the street. The home next door has a pool and cage on the back
similar to ours.
October 17, 2001
There have been several men
at the site, continuing the preparation of the site until this morning.
Then an army of workers arrived and the trucks started coming. They poured
the slab today. It was quite a production. I don’t know how many people
were involved – but there were many.
And I don’t know how many trucks of concrete they used – but
many. They were pouring most
of the morning. At one point
there were two trucks on the site and two on the street waiting. Very
impressive. A crew of about 10 spent the afternoon compacting and
smoothing. It looks good.

October
18, 2001
They are getting ready to
frame. Two things convinced us. (1)-
They delivered materials to the site. Lots of them to start the framing. (2) – We met the construction
supervisor, Phil, and he told us so.
We also talked to Joyce
from “Backyard Aquatics.” They plan to start the pool on Tuesday. Next
week should see lots of changes.

October
23, 2001
It
rose from the earth. I drove by the house lot about 7:15 and it was
quiet. Then - about 10:15, we heard the framing was started.
We drove over and - a house was taking shape. By the end of the day, the
framing was well on the way. We checked and the pool people had been there
also. The location and shape of the pool is laid out and it even
looks like we planned.

October
25, 2001
They
have had a large crew working on the house for the last two days with
highly visible progress. The roof is installed and the first layer of
protective material is applied. The inside is framed and ready for the
installation of the electrical and plumbing rough-in.
The
pool installers have been busy also. The pool hole is dug. What's
next is a mystery to me - but it will be fun watching it take shape.

October 26, 2001
The framing crew continues
their work. The rooms are taking shape and the layout and sizes can now be
appreciated. We hang around and try to picture how it is all going to look
in a few weeks.
The pool has not progressed
for a couple of days. But --

October 29, 2001
This morning saw a large
dump truck and front end loader at the site at 7 AM. These tools were used
to remove the material in front of the garage in order to pour the
driveway. It’s quite a wide drive as you can see. We went by in the
early afternoon and the pool people had just arrived. They were working on
the steel and wire to get it in the final position for spraying on the
gunite.
October 30,
2001
A quiet day on the home
site. Today was spent discussing a small change in the family room window.
We want it a little smaller then it is and after some discussion with the
construction people, it was agreed.
There
was activity in the pool. They seem to have finished the preparation for
gunite – even plumbing in what will be the drain in the bottom. They
also spent some time framing the Lanai to Pool interface. Looks good
according to Linda and Duncan.
October 31, 2001
Well – the day started
with a call from "The Plantation." Seems they will put in a
smaller window if I go get it. So – off I went to Home Depot.
After educating myself - I got what we wanted and dropped it off
Waterbridge Court.
The small framing crew
continued working installing interior walls. All else was quiet.

November 1, 2001
The framing crew continued
working on interior walls. The family room window was framed for the
smaller window. A crew started on the roof installing shingles. They
stopped working about dusk and are about ½ finished. The special shingles
really look good.
November 3, 2001
The constant activity
continues. There are several guys working on the roof – installing
vents, trim and finishing off the shingles. There are 3 guys inside
finishing up the interior framing. Then, in the last two days, they’ve
been installing the electrical, smoke alarms, cable, phone, vacuum, and
air handling systems. It is showing progress daily.
November 7,
2001
There was activity over the
weekend. They finished up the
services that needed to be installed in the walls – electric, plumbing,
vacuum, pool alarms, smoke alarms, air handling, bathroom vents, The
windows went in today and the large doors are there and ready for
installation.
Linda
and Duncan are ready to move in.

November 8, 2001
Yesterday they insulated
the walls and ceiling. A large delivery of siding was made and ready to
install. The bricks and mortar are also on site.
The pool had the
Gunite “shot” in place on Monday and we can now see it's size and
shape. It looks like just what we wanted.
November 10, 2001
The constant activity has continued. The brick on the front of the house
has been started and is ½ complete. All the house exterior doors are in.
The installation of the front door made the entry start to look inviting.
The wallboard has been
distributed to various places in the house. This is to put it where it’s
needed I guess. They are not normal 4’ X 8’ sheets – but much
larger. How they handle them up onto the vaulted ceiling must be something
to see.
Today we received
our closing date of 12/19! That
is excellent. We will celebrate Christmas in our new home.
We continue furniture
shopping and now have ordered most everything we “need.” From here on
we will shop for the remainder of the house.

November 12, 2001
They finished up the brick
work today – and they started installing siding. It looks great. The
wallboard is ready to go on we think and I’m told they do it very
quickly.
We’ve been noticing that
our house is situated such that it’s visible for ½ mile as you drive
towards it on Plantation Boulevard. We will have to pay close attention to
it’s appearance from both directions.
November 14, 2001
The last two days have seen
lots of progress. The roof has had the last of the trim work completed,
the pool has had the tile on the top installed, the siding is making
progress and the wallboard has been completely installed. Walking around
inside now feels like a house. My little digital camera hasn’t been able
to take a good picture – but I’ll keep trying.
November
18, 2001
The wallboard is now
complete and the guys who tape and mud have spent two days on the job. They’ve taped and floated all
the joints and are ready to prepare for the final coat tomorrow. The
siding is almost done. The outside is looking like a real house. This
picture is a “computer enhanced” photo of what it might look like in a
month or so – without landscaping.
November 20, 2001
The siding is complete all
around. Looks great. The interior walls now have been mudded a couple of
times and the “orange peel” surface was sprayed on yesterday
afternoon. They look ready for paint. The trim and all the cabinets and
doors were delivered today.
Today the pool folks were
busy installing all the mechanical stuff and finalizing the plumbing. They
have the forms in to pour the footing for the cage.
The driveway and walk areas
were prepped for pouring concrete also.
That should all take place soon.
We drove by after dinner
tonight and there were guys working in the dark. They had aimed a pick-up
truck, with it’s lights on, towards the front door.

November 22, 2001
Happy thanksgiving
The house is looking more
and more complete every day. This view shows you how the kitchen looks
today. They are getting ready for some major changes in the next week. The
trim, cabinets, counter tops, doors, and many gallons of paint are all now
in the house and ready to be installed. It’s a very exciting time.
November 24, 2001
We had a very nice
Thanksgiving Dinner with our future, across the street, neighbors. Since
then, the crew has been working on installing the doors and trim. We
ordered all of the appliances and asked for delivery on 12/13. We got the
major ones through GE and the TV’s at Sears (Samsung Electronics).
November
26, 2001
Work continues at
Waterbridge Court. Today we met with the Construction Supervisor , Phil,
at the house. We wandered around and asked lots of questions. He answered
them all and took some action where some was needed. The painters were
there and sprayed most of the inside.
Men were working on the driveway and walk – getting those ready
to pour. The cabinets are in the garage and ready for installation. A very
busy construction site.
November 28,
2001
It has been a busy week so
far. The cabinets are in the kitchen and all the bathrooms. The
countertops are on in the kitchen.
The driveway and walk have
been poured and they are both ready for pavers.
The pool people have been
busy. They poured the apron around the pool and the footing for “the
cage.” They cleaned all the debris off the lanai and textured the pool
apron and the lanai.
We met with the landscaper
yesterday. After an emotional beginning and a long morning in his SUV, we
selected a “Landscaping Package.” This was accomplished without the
aid of any plans, landscaping visual aids like photos or even an example
of what we are entitled to. Far from a professional presentation.
We went to the house about
5 and there were two men “grading” the lot. Our "Landscaping
Package" will be installed soon.
December 3, 2001
The landscaping is
continuing. They seem to have
run out of sod and are waiting for more. They started erecting the “Cage”
today and did some work on the inside. The pool is starting to look
inviting.
Flooring is down in a
couple of the bathroom and tile is in the foyer and the baths also.
We had our 2nd
progress meeting with the Construction Supervisor, Phil, today and he was
able to bring us up to date and answer all our questions. He has
confidence we will be ready to close on December 19, 2001.
December 5, 2001
The landscaping is almost complete. They are short just a little turf.
Inside is progressing also. The effort the last few days has been on the
tile in the bathrooms and foyer. It's now complete and looks great.
The major addition in the last few days is The Cage. Linda is ready and
just waiting for water.
December 12, 2001
Well – things have been happening – mostly on the inside. They have
finished the landscaping. Inside, they have been finishing off the
electrical work, plumbing and putting down floors. It is now a week to
closing and they are heading towards finishing that day.
I have no photos to add – Linda and I took a couple of days and went to
Disney World to see all the Christmas Decorations and Attractions.
December 13, 2001
There continues to be no electricity in the house. That became important
today. All the remaining appliances were delivered. But – they arrived
at 6:20 PM – and it is dark at that time. They didn’t feel it was safe
to try to move all those appliances around in the dark – let alone
install them. So – back to
Ocala they went. The delivery has since been rescheduled for 12/17.
December 15, 2001
Still no electricity. The pace has slowed. They seem to apply the resources
they have to the “Next” house to close. Ours isn’t it yet.
We
had a meeting with the construction supervisor. He assured us he would spend 100% of his time in
our house making sure it is finished – on time and correctly.
Today – the carpet man and girl were in the house all day. They installed
all the padding and most of the carpet.
It looks great.
The
Interior Decorator from Babbette's came over this morning and spent a hour
with us. He'll help selecting the rest of the furniture and other items
we'll need.
Though I haven’t mentioned it, all the mechanicals have been installed
during this time.
December
17, 2001
The house was finally electrified. The construction Supervisor called about
10 and said it was done. Today
they worked more on the pavers in the walk and drive, finished the
installation of the rug and cleaned the floors. Not much else seems to
have been done.
The
pool installers were supposed to be there all afternoon - they weren't.
The appliances were supposed to arrive again today between 1 and 5. They
didn't. We'll try again tomorrow - third times the charm? It may actually
be fortuitous – they couldn’t carry them in through the front door
because of the newly installed pavers.
The
closing is now about 32 hours away and there is still lots to do.
December
18, 2001
Today was “Finish Day” I guess. There were at least 10 folks descended
on the house this morning and patched, painted, cut, trimmed, finished the
pool, and anything else that needed doing. The appliances even arrived.
They all got installed – except the refrigerator. It has to go in
through the front door and the pavers aren’t set enough yet. Tomorrow.
We went over about 5 and the painters were just leaving. Jean (Our Sales
Person, Our Florida Daughter) came over and we all wondered at how much
they had done in one day. It looks great. Bill, our landlord, also stopped
by. The house looks great. We are ready !!
December
19, 2001
Today was “Closing Day” on this adventure.
We started with a “Community Orientation.” This was a very informative
session explaining all the intricacies of living here. Next we did the “Final
Walk Through” with the construction supervisor. This was a little
rushed, but ended with a checklist of things yet to do to finish the
house. Then – off we went to the Attorneys Office for “The Closing.”
This went very smoothly with and only lasted about ½ hour.
Back to Our House. We stopped at the Storage Place along the way and filled
the van with various boxes. We stopped at our rental home of the last 2
1/2 months and got Duncan. Then we went to our new Home. We unloaded the
van and then went to dinner at “The Tara Club.
December 20, 2001
Today was “Moving Day.” We started early. The Construction Supervisor
was on the job and already organizing things that needed fixing.
Linda spent the day unpacking and orchestrating the various delivery trucks
and service personnel. I used the van and a borrowed pick-up truck to make
trips to the storage shed and back.
All the furniture arrived as planned with the last being the bedroom set.
It arrived at about 6:30 PM and the guys got it assembled and in place at
just about 7:30.
We stayed here to watch some TV and revel in our new surroundings until 9. Back to the rental house to spend
our last night there.
Think of it – 80 days ago, this was an empty lot.
Now it’s our dream, retirement home. The Plantation Construction crew
has done an outstanding job of organizing and implementing this task.
Somehow the Construction Supervisor pulls all the contractors together to
get the job done.
Linda has pulled together all the necessary people
and things to get us comfortably in our new home on schedule - and color
coordinated. All this without a Gant Chart.