INTERNATIONAL SPACE STATION DEVELOPMENTS
US-Russian Projects

	The International Space Station project continues officially on 
schedule. Fabrication and test of hardware continues around the world, but 
there are reports that delays are coming unless changes are made soon, 
especially on the Russian side where funding problems are threatening the 
schedule for the first ISS crew launch. Early in 1996 these concerns were 
aired at the highest levels of contact. In July, the seventh meeting of the 
Gore-Chernomyrdin commission (also known as the Intergovernmental 
Commission on Economic and Technical Cooperation) got underway to 
discuss ISS funding problems, and open issues and new business. 
	The agenda included talks on trade, finance, taxes and investment, 
intellectual property, energy research, nuclear materials, biological 
weapons reductions, joint crime fighting, internet infrastructure, joint 
research of Lake Baikal, and joint space programs. In the sphere of space 
programs there was progress in planning the  alpha-magnetic 
spectrometer for antimatter research in space, a joint project of the 
United States, Russia, China, Germany, Holland and Switzerland. A new 
assembly sequence for the International Space Station was initialed for 
further development and publication in the fall of 1996. Talks were also 
held about joint missions planned for studies the sun and Pluto. Another 
result of meeting was a final version of the agreement on commercial 
launch of western satellites which is to be approved by the Russian 
government. 
	Funding problems of the Russian Service Module were discussed but 
no results were announced. Russian press reports claim that the payments 
made to Russia for the cooperative flights of the Shuttle and Mir and the 
International Space Station are only covering 5 to 8% of their true cost. 
Russian Prime Minister Viktor Chernomyrdine has been unable to remedy 
the situation. The Khrunichev factory is facing the worst problem and is 
nearly out of time to keep to the existing schedule for Service Module 
development. The Russian government did guarantee a loan to Khrunichev 
covering short term costs, but not enough to pay subcontractors. 
According to NASA, September is the deadline for the project to get back 
under control and that would be by running 3 shifts, after that the launch 
has to be delayed which also delays the first crew launch.
	NASA Administrator Dan Goldin also participated and held talks with 
his counterpart, Yuri Koptev, and presented flags returned from space to 
the Gore and Chernomyrdin. On July 15, there was a joint conference call 
scheduled for Gore and Chernomyrdin to talk to the Mir-21 crew but Gore 
declined the opportunity and Goldin and Koptev stood in for them to make 
the call. During a joint call to Mir, Koptev asked about the condition of Mir, 
and the cosmonauts said that it was in great shape with a few minor 
problems. They also said that the Priroda module activation was going 
according to plan. The session was closely followed by Russian and 
American businessmen who use the commission meetings to iron out 
problems in international business dealings. The next meeting of the 
commission will be held in the United States in December.
	One of the key factors in establishing Russian-US cooperative 
Shuttle-Mir flights was the US insistence that a deal between Russia and 
India for cryogenic rocket engine technology be cancelled. It was 
suggested by the Russians that if a corresponding sale was found the deal 
would be redrawn excluding sale of the technology in question. The result 
was a $400 Million US project of flights to Mir. Now, India has made 
significant progress in its program to develop indigenous technology to 
replace that denied by the US State Department under the MTCR (Missile 
Technology Control Regime). The Indian Space Research Organization 
reports that it has completed design of a cryogenic engine for the 
Geostationary Launch Vehicle (GSLV). The Hydrogen-LOX engine has 7500 
kg. Thrust (461 Isp, 740 sec. duration and restartable) and will enable 
launch of 2500 kg. satellites. Contracts for he construction of the engine 
have been signed while design is underway for larger engines with 12,000 
and 16,000 kg. thrust. The engines will replace engines bought from Russia 
(without the manufacturing technology) in 3 to 4 years. The first Russian 
engine will be delivered around the end of the year, and 3 more will follow 
at 6 month intervals. 
ESA Projects

	The ESA Automated Transfer Vehicle (ATV) project entered the final 
phase before full scale development expected in September 1996 with 
Aerospatiale is the prime contractor. The Crew and cargo Transport 
Vehicle (CTV) project using the ATV as a basis is running slightly behind 
the ATV. NPO Molniya and TsAGI are participating in the development of 
the CTV capsule by providing flight results from the BOR series of flights 
in the 1980's to compare to European theoretical results. A prototype 
capsule is expected to be launched in 1999 as a supplementary payload on 
a Photon satellite. Operation flights will be made after 2000 to the ISS 
with the ATV and CTV. The CTV is expected to replace the western 
partners reliance on the Soyuz TM as an emergency transport. 
Japanese Projects

	In Japan, a two and a half month long Critical Design Review for the 
JEM module was said to be successfully completed in February 1996. 
Hundreds of issues were resolved, for example an incompatibility of the 
JEM manipulator and the Space Station RMS. Some of the remaining issues 
included EVA tests and planning, structural loading of JEM payloads and 
payload envelopes on the shuttle. Launch of JEM is planned for 2000.


SHUTTLE-MIR

		
Mir Operations

	The last Mir module, Priroda, was launched on April 23, to complete 
the Mir complex and carrying NASA equipment for Shannon Lucid's mission. 
NASA requested the module be docked as soon as possible since the module 
was late and missed the first part of Lucid's mission. The Russians 
complied and shortened the approach from 9 to 3 days, docking Priroda on 
April 26. A total of 600 Kg. of equipment from Russia, NASA, Britian and 
Germany are included in the module designed mainly for Earth observation, 
biological and space exposure research.
	The Russian crew of Yuri Onufriyenko and Yuri Usachev continues to 
host NASA astronaut Shannon Lucid. On March 15, the cosmonauts 
performed an EVA to install a second Strela crane to the Mir base block to 
allow solar array transfers from the Docking module to Kvant. One notable 
event was the commercial filmed for Pepsi, as the cosmonauts unfurled a 
collapsible Pepsi can, as part of a commercial agreement with Pepsi to 
help it promote its products. The nylon and aluminum expandable can was 
Pepsi can on EVAPhoto: PepsiCo Inc.
built by International Space Enterprises, San Diego. It was delivered by 
the Progress flight in May and the can will be returned aboard a Soyuz. The 
crew also filmed inside the Mir base block.
	Another EVA on May 21 installed the MCSA (Mir Cooperative Solar 
Array) on the Kvant module. The MCSA was delivered by STS-74 in late 
1995. The MCSA is testing future space station solar array elements and 
provides more power to Mir. On May 25 the cosmonauts went EVA again to 
unfurl the MCSA which was equipped with a hand crank type deployment 
mechanism instead of electric drive units on some other Mir arrays., 
Another EVA on May 31 was to done to install Moms-2P multispectral 
stereoscopic camera onto Priroda. They also installed a EVA hand rail onto 
Priroda.  An EVA on June 13 completed another phase of the Pepsi 
commercial, and the cosmonauts added a additional section of truss to the 
bottom of the Rapana truss on Kvant. The enhancement for Rapana will 
allow better measurements of the space environment and test a design 
planned for use on the International Space Station.
NASA Operations

	US astronaut Shannon Lucid set a new US record for duration of 
spaceflight on Mir in July. John Blaha is scheduled to be launched on STS-
79 to replace Shannon Lucid on Mir. The launch date for STS-79 was 
initially threatened with delay by engine troubles on the Shuttle Carrier 
Aircraft carrying Atlantis back from its landing at Edwards AFB. This 
would be only the first of problems encountered trying to put Atlantis 
back into orbit. Soon after rolling the STS-79 stack to the launch pad it 
had to be rolled back to the VAB to avoid the passing hurricane Bertha. At 
the same time the SRB's from Columbia's STS-78 launch in June revealed 
some hot gas leakage into the "J" insulation flaps. Just after rolling the 
stack back to the pad it was decided to replace the STS-79 SRB's with 
those being prepared for STS-80 using an old adhesive deemed safer than a 
new type used on the previous flight. The launch was delayed more than 5 
weeks giving Lucid the chance to break the record duration in space for a 
female as well as the US record. The experiment program to be performed 
by John Blaha will be begun by Lucid during her extended mission. Lucid 
continues to report that the mission is going well, with no significant 
problems. 
Future Mir Operations

	Progress M-32 was scheduled to resupply the current Mir crew but 
its launch on July 22 was delayed initially due to the loss of 2 Soyuz-U 
boosters carrying photo-reconnaissance satellites. The investigation 
discovered a problem with changes in payload shroud construction 
unrelated to the type used on Soyuz or Progress payloads clearing the 
Progress for launch. On July 25 launch was attempted but was scrubbed in 
the last seconds due to a propellant system problem which could be fixed 
quickly. Launch was initially scheduled for 24 hours later but soon was 
delayed until Aug. 1 to change the booster. Unexpectedly the date again 
shifted, this time back a day to July 29. Its cargo included: 334 kg. 
scientific equipment, 290 kg. food, 300 kg. water, 46 kg. oxygen, 80 kg. 
personal supplies, and propellants, totaling 2400 kg.
	The Mir-22 crew's flight was also delayed in June by 40 days, to 
August 14, due to delays in funding and construction of the booster.,The 
Mir-22 mission is planned to last about 200 days. It also became 
necessary to lower the orbit of the station in early July to allow the used 
of a Soyuz-U booster with 275 kg. less payload capability than the 
preferred Soyuz-U2. The Soyuz-U uses a less expensive fuel and will save 
the Russians money. It was even reported that the cosmonauts were to 
loose 6 kg. weight to lessen constraints on payload capacity. The effect of 
the delay has also purposefully delayed future planned flights. Russia 
wants to do this to delay construction of new spacecraft and boosters to 
save costs. International partners have little choice but to go along, the 
Mir-22 and Cassiopeia project has been delayed, and the German flight 
planned for December is now expected no earlier than January 1997. After 
the problems launching Progress M-32 the Mir-22 crews launch was again 
delayed to Aug. 19 due to the extra processing needed for the Progress 
launch. 
	The joint German, Russian, American Inspector sub-satellite project 
is progressing to launch in August 1997. Inspector will be launched on  
Progress-M and deploy to fly around the complex by remote control to be 
retrieved by a later shuttle flight. Russian press reports claim that Mir 
may continue to be operated until 2002, but this would require occupation 
due to the unpredictability of breakdowns.
International Mir Missions

	NASA officials went to Ukraine in March to start preparations of the 
biological experiment program to be carried out on the flight of a 
Ukrainian astronaut on the shuttle in October 1997. In March an agreement 
was made to launch a Japanese experiment payload to Mir on a Progress 
late in 1996. The experiment was to be performed for 2.5 months. 



LAUNCH SYSTEMS

		
Proton

The Proton launch system suffered a setback in February when the Block-D 
fourth stage malfunctioned while launching a Russian Raduga 
communications satellite. Quick investigations revealed the likely cause 
was a fault in the manufacture of the stage and future launches were 
relatively quickly cleared to proceed. Khrunichev officials were quick to 
distance them selves from the problem noting that the problem was not 
really in their rocket but in the upper stage made by RKK Energia and had 
been procured and managed under a Ministry of Defense order.
On April 9 the Astra-1F satellite successfully launched by a Proton 
dispelling any fear of booster problems. The State Commission for Proton 
launches was supervised by none other than the Commander of the Russian 
Space-Military Forces, Colonel General Vladimir Ivanov. It was the first 
launch marketed by the joint ILS firm comprised of the Khrunichev Space 
Research Center, RKK Energia, and Lockheed-Martin. The launch cost was 
$60 Million and 19 more flights have been contracted by ILS. The Proton's 
Tempo-1 launch was delayed from June to December, at customer request 
according to Khrunichev. Khrunichev has spent $40 Million in upgrades to 
the launch site including a new communications system, new power 
generators and a new hotel. The launch quota agreement amended several 
months ago was finally submitted to the Russian government for official 
approval by the RSA in May.
	ILS got more business in March when Asiasat cancelled a Long March 
contract in favor of a Proton launch in 1997. This followed failures of 
Long March including one which killed several people in February. Great 
Wall representatives said its busy schedule and low Russian prices were 
the real reasons Asiasat abandoned the Long March, and that the decision 
was made before the latest accident., 
Soyuz

	A Soyuz-U launch failed on May 14 to launch a photo-reconnaissance 
satellite planned to carry out an order for photos by the American firm 
Aerial Images in a project called 'Spin-2'. The booster shroud failed about 
a minute into the flight and signals were lost from the payload after 6 
minutes. The problem was immediately obvious and news reports the same 
day identified the problem. The Baykonur launch was insured for $2.7 
Million by Sovinformsputnik which will compensate Aerial Images in turn 
when the funds were made available.A second Soyuz-U launch failed at 
Plesetsk on June 21. The payload was another photo-reconnaissance 
satellite and the nature of the failure was identical. Both failed flights 
used the same type of payload shroud which had undergone a recent 
manufacturing change blamed for the failures.
	A proposal of the RSA to carryout commercial launches for 
Aerospatiale and Arianespace using Soyuz boosters has been approved. 
TsSKB-Progress and the RSA will negotiate the establishment of a joint 
stock company with the French partners although no technology is to be 
exchanged.
	The French Minister for Post, Telecommunications, and Space signed 
the French-Russian agreement in June to form the Starsem company to 
market the Soyuz. The company will be owned 50-50 between the 2 
countries, Aerospatiale will own 35%, Arianespace 15%, TsSKB-Progress 
25% and the RSA 25%. The first launch is hoped for 1997, and 2 more in 
1998, building to a steady rate of 4-5 launches a year. Aerospatiale may 
make modifications to the Soyuz if needed. One of the main reasons the 
French joined the joint venture was the fear that a US company might beat 
them to it after the successful example of the ILS venture. The expected 
market is primarily 'big LEO' communication satellite systems launch and 
refurbishing which is not economically attractive on the Ariane 5. Cost of 
launches is expected to be about 175 Million Francs. Launches may take 
place from Baykonur or Plesetsk.
	DASA was also included in some planning but opted out of the 
venture, but the option for other European partners to join at later date 
was put into the agreement. The agreement also can also be expanded to 
include future versions of the Soyuz like the Soyuz-2 (Rus) and manned 
uses of the boosters. For now it is planned to launch up to eight 500 kg. 
class satellites at a time on either Soyuz and Molniya boosters using a 
new upper stage or bus called Ikar to deliver multiple satellites into 
proper orbits. Ikar will be developed jointly by Russia and France. 
Tsyclon

	Rockwell's Space Systems Division announced in July that it will 
market the Tsyclon boosters produced by NPO Yuzhonye. They also will 
provide payload integration services. Shortly afterward it was announced 
that Boeing had bought Rockwell's Space division which means Boeing has 
a hand in marketing both the Tsyclon and Zenit boosters (marketed by Sea 
Launch which includes Boeing) both produced by Ukraine.
Energia-M vs Angara

	Energia-M seems to be the project that will not die. Reports now say 
that a new competition is being held by the RSA to decide between support 
of Angara or Energia-M. RKK Energia claims that existing Energia 
infrastructure would give the Energia-M an advantage, but the enormous 
cost of maintaining that infrastructure is also a large hindrance. The 
military still plans only on the Angara and the RSA has taken no role in 
Angara development favoring Proton-M instead which won an earlier 
competition with Energia-M, so Energia's effort to find a role for the 
Energia-M seems to be doomed since the major players have already made 
their choices.
Start

	The Komplex Scientific Technical center signed an agreement with 
an Austrailian company to make Start launches from the Woomera launch 
center. They must first find customers who require launch from Australia 
and hope to woo mobile communications and environmental monitoring 
payloads for a launch as soon as late 1998. In related news, the first Start 
launch from the Svobodnyy Cosmodrome is scheduled for the third quarter 
of 1996. 
Rokot

	Brazilian Space Research Agency officials visited several space 
industry sites around Moscow in March and held talks with RSA head Yuri 
Koptev. Press reports also linked the Brazilians with Khrunichev where 
rumors said a deal was being made to launch Rokot boosters, but nothing 
was officially announced. Khrunichev's Rokot joint venture with Daimler-
Benz Aerospace ran into a problem in May as Khrunichev ran out of funding 
to complete construction of the 3 stage version based on an RS-18 (SS-
19) ICBM. Germany has offered to reduce Russia's debt to Germany in 
return for financing of the project. 60 of the ICBM's are thought to be 
usable as boosters and in June one was tested successfully.
Shtil

	In October, the first Russian Navy research satellite will be 
launched by a Shtil booster on a ballistic missile submarine in the Barents 
sea. The Kompas satellite is to conduct geophysical and electromagnetic 
research which could aid in predicting earthquakes.
Kosmos

	The Polet association has signed a contract for launch of 26 small 
communications satellites for Final Analysis Co. Four Kosmos boosters 
will be used in a swap of launch service for market rights to sell the 
service in Russia (similar to the deal struck for Iridium launches with 
Khrunichev). The satellites will be used for data services and will follow 
1 existing and 1 planned satellites launched on Kosmos flights as 
secondary payloads.
Engines

	In other launch industry news, on Cosmonautics Day Boris Yeltsin 
celebrated the RD-180 winning the potential billion dollar Lockheed-
Martin Atlas contract by visiting NPO Energomash in Khimki. The Russians 
will get an additional windfall from the project since the RD-180 will be 
reused in the Angara rocket family. The RD-180 program is headed by 
Feliks Chelkis (Chief Designer). Production will start in July 1996 with 
testing starting in November. In addition to Energomash executives, 15 
aerospace industry executives forming the cooperative Kompomash 
corporation attended the event looking for government aid. The 
industrialists asked for a official policy on protectionist measures for 
domestic and international sales, extra funding for research and 
development, attention to timely and complete payment to industry, and 
guarantees of loans and international business deals. Yeltsin reportedly 
promised full settlement of debts to the defense industry at the meeting. 
He also announced that he was directing Yuri Koptev and Oleg Soskovets to  
draft an edict ending taxes and export duties for the space industry and 
promised 2 Trillion Roubles of aid outside of the federal budget to the 
industry.  In return, Kompomash corporation leaders announced their 
support of Yeltsin's presidential campaign noting that it was not time to 
change leaders and change could be dangerous.,
	Energomash is continuing development of other rocket engines 
including the RD-704 tri-propellant engine targeted for use on single 
stage to orbit boosters yet to be developed. Other engines being developed 
are the RD-169, RD-185 and RD-190 for the Riksha light launcher. It is 
estimated that the RD-180 will be in production for 20 years and at least 
100 engines are earmarked for use in the USA.




Sources: FBIS, Novosti Kosmonavtiki, BBC Monitoring, wire services, Press Releases, OMRI Daily Digest, personal correspondance. An expanded and referenced version of Cosmonautics news including space center news, space industry, military space forces and related news is available from the Russian Aerospace Guide. For samples and back issues visit the Russian Aerospace Guide web site at http://home.attbi.com/~rusaerog/