| 2005 Budgeted Projects | |||
| Project | Cost Est. | Totals | Notes |
| Capital Projects | |||
| Rebuild Walls | $30,000.00 | Capital project | |
| Repaint railings and lamp posts | 1000 | ||
| A-Block lawn improvement | 500 | ||
| Remove dead trees H/K Blocks and CHR | 1000 | ||
| Repair canal erosion (with RA) | 900 | ||
| Planting in K-Block entry | 300 | ||
| Paving and Sidewalks | |||
| Restripe K-Block parking spaces | 500 | ||
| Restripe C-Block | 500 | ||
| Paint curb/firelane in H/K-Block | 300 | ||
| Other Landscaping | |||
| Miscellaneous | |||
| Totals | $35,000.00 | ||