Range Tasks |
Persons Needed |
| n |
Apply Trim to
Range Bump-Out
|
3 |
| n |
Rub
Down interior walls
|
1 - 3 |
| n |
Paint interior partition walls
|
1 - 3 |
| n |
Paint metal doors / frames |
1 |
| n |
Paint Exterior Walls |
1 - 3 |
| n |
Paint
backstop
|
1 - 3 |
| n |
Install radiant heat system |
1 - 4 |
| n |
Frame
bathroom partitions
|
3 |
| n |
Install Rough Plumbing / Assist Plumber |
2 |
| n |
Install Plumbing Fixtures/ Assist Plumber |
2 |
| n |
Install blocking for handicap bars in bathrooms |
1 |
| n |
Apply plywood to kitchen wall(s) |
2 |
| n |
Apply sheetrock to kitchen walls |
2 |
| n |
Rough plumbing Inspection |
1 |
| n |
Apply sheetrock to bathroom walls |
2 |
| n |
Box In Tubing for Range Heat |
1 |
| n |
Install kitchen cabinets |
2 - 3 |
| n |
Install microwave cabinet & venting |
2 |
| n |
Frame Closets in Kitchen Area |
2 |
| n |
Relocate Six bar joists |
6 |
| n |
Cement / Block wall around bar joists |
2 |
| n |
Frame / Pour Pads for Outside Equipment |
4 |
| n |
Stage steel plates for installation |
4 |
| n |
Hang steel plates |
6 |
| n |
Weld Steel Plates |
3 |
| n |
Attach metal stand-offs to steel plates |
4 |
| n |
Attach plywood to metal stand-offs on steel
plates |
4 - 6 |
| n |
Install
metal ceiling |
3 - 5 |
| n |
Frame
out ceiling over shooting stations |
4 |
| n |
Install
bullet-proof ceiling over firing line |
3 - 5 |
| n |
Install
suspended ceiling in common areas |
3 - 5 |
| n |
Install
doors in common areas / Closets |
3 - 5 |
| n |
Install tile on bathroom floors |
3-5 |
| n |
Install tile on meeting room / common area
floors |
5-6 |
| n |
Assist
Randy Parker in electrical wiring tasks |
1 - 4 |
| n |
Assist
in installation of Heat Pump |
1 - 3 |
| n |
Cleanup,
cleanup, cleanup. |
1 |